2. Consider the data given in the following table and give what is asked. Immediate Normal Time Crash Time Activity Normal Cost Crash Cost ($) Predecessor (Days) (Days) 4. 2 200 400 B 3 300 600 200 200 D. В, С 600 650 D. 2. 500 900 A. Create a Gantt Chart using the normal time. 8. Create an AON and AOA network diagram. C. Determine the critical path. D. Determine the crash cost per period. E. Suppose the owner of the company wants to limit the project time within 11 days, which activity/ies should you crash?
2. Consider the data given in the following table and give what is asked. Immediate Normal Time Crash Time Activity Normal Cost Crash Cost ($) Predecessor (Days) (Days) 4. 2 200 400 B 3 300 600 200 200 D. В, С 600 650 D. 2. 500 900 A. Create a Gantt Chart using the normal time. 8. Create an AON and AOA network diagram. C. Determine the critical path. D. Determine the crash cost per period. E. Suppose the owner of the company wants to limit the project time within 11 days, which activity/ies should you crash?
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
100%
NOTE: Answer letter E only.
![Patagraph
Styles
Edting
2. Consider the data given in the following table and give what is asked.
Immediate
Normal Time
Crash Time
Activity
Normal Cost
Crash Cost ($)
Predecessor
(Days)
(Days)
A
200
400
B.
4.
300
600
200
200
B, C
3
2
600
650
D
500
900
A. Create a Gantt Chart using the normal time.
8. Create an AON and AOA network diagram.
C. Determine the critical path.
D. Determine the crash cost per period.
E. Suppose the owner of the company wants to limit the project time within 11 days, which
activity/ies should you crash?](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Fac0cd4d5-5e8f-43fe-abef-395799e1a1ae%2Fcbabf78c-8cca-476f-9425-1666c5843806%2F31vh4hd_processed.jpeg&w=3840&q=75)
Transcribed Image Text:Patagraph
Styles
Edting
2. Consider the data given in the following table and give what is asked.
Immediate
Normal Time
Crash Time
Activity
Normal Cost
Crash Cost ($)
Predecessor
(Days)
(Days)
A
200
400
B.
4.
300
600
200
200
B, C
3
2
600
650
D
500
900
A. Create a Gantt Chart using the normal time.
8. Create an AON and AOA network diagram.
C. Determine the critical path.
D. Determine the crash cost per period.
E. Suppose the owner of the company wants to limit the project time within 11 days, which
activity/ies should you crash?
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 4 steps with 3 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Recommended textbooks for you
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Business in Action](https://www.bartleby.com/isbn_cover_images/9780135198100/9780135198100_smallCoverImage.gif)
![Purchasing and Supply Chain Management](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
![Production and Operations Analysis, Seventh Editi…](https://www.bartleby.com/isbn_cover_images/9781478623069/9781478623069_smallCoverImage.gif)
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.