Consider the following data for a project to install a new server at the Northland Pines High School: Immediate Predecessor(s) Activity Activity Time (days) ABCDEFGHI 3 5 A 3 A 3 B 1 5 B B, C 2 D, E Н 6 3 6 F F G, H, I b. Calculate the critical path for this project. The critical path is A-B-F-H-J and the project duration is 25 days. (Enter your response as a whole number.) c. How much slack is in each of the activities G, H, and I? On Activity Activity Time (days) Slack critical path? (days) G 2 No 6 H 6 Yes 0 I 3 No 3

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Question

Can you show me how to get that answer please? 

Consider the following data for a project to install a new server at the Northland Pines High School:
Immediate Predecessor(s)
Activity
Activity Time (days)
ABCDEFGHI
3
5
A
3
A
3
B
1
5
B
B, C
2
D, E
Н
6
3
6
F
F
G, H, I
Transcribed Image Text:Consider the following data for a project to install a new server at the Northland Pines High School: Immediate Predecessor(s) Activity Activity Time (days) ABCDEFGHI 3 5 A 3 A 3 B 1 5 B B, C 2 D, E Н 6 3 6 F F G, H, I
b. Calculate the critical path for this project.
The critical path is A-B-F-H-J and the project duration is 25 days. (Enter your response as a whole number.)
c. How much slack is in each of the activities G, H, and I?
On
Activity
Activity
Time (days)
Slack
critical path? (days)
G
2
No
6
H
6
Yes
0
I
3
No
3
Transcribed Image Text:b. Calculate the critical path for this project. The critical path is A-B-F-H-J and the project duration is 25 days. (Enter your response as a whole number.) c. How much slack is in each of the activities G, H, and I? On Activity Activity Time (days) Slack critical path? (days) G 2 No 6 H 6 Yes 0 I 3 No 3
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.