Job Flow Time (min) 1 2 3 4 5 6 minutes Makespan: Average flow time: minutes In what order would the jobs be processed using the SPT rule? The SPT sequence is -Select- -Select---Select-- -Select- -Select-- -Select- Compute the average flow time after each job is completed. Round your answer to the nearest whole number.
Q: 2. (a) A recent study found that small and family firms were more centralised in terms of…
A: The process of decision-making involves identifying a problem, acquiring information about the…
Q: With reference to the table below, determine the activities that are on the critical path and the…
A: A network diagram shows the link of each task with the duration taken by each activity with respect…
Q: The Baton Rouge Police Department has five detective squads available for assignment to five open…
A: CasesSquadABCDE11034521281271221313252426841473727520712630
Q: A comparative market analysis (CMA) MUST include: a) the square footage of the property b) school…
A: A Comparative Market Analysis (CMA) stands as a fundamental tool in the realm of real estate,…
Q: Which of the following will help ensure that interaction with remote members will have the best…
A: With the advancement in technology, organizations have started conducting virtual meetings. These…
Q: Suzuki is a company that manufactures motorcycles. It produces 450 motorcycles a month. It buys…
A: The objective of the question is to calculate the Economic Order Quantity (EOQ), the number of…
Q: Answer the following: Use a data table to determine the range of costs you might encounter when…
A: Here, I will determine the range of costs that we will encounter,
Q: The Green Cab Company has a taxi waiting at each of four cabstands in Evanston, Illinois. Four…
A: The distances, in miles from the waiting taxis to the customers - Cab site CustomerABCDStand…
Q: The Pinto was a small subcompact car manufactured by Ford in 1971 in the face of looming competition…
A: The Ford Pinto crisis stands as a somber chapter in corporate history, epitomizing the intersection…
Q: Using the EVUPI method, what will be the expected value? Success Moderate Success Failure 0.4 0.5…
A:
Q: QUESTION 3 Given the following inventory information, construct an (a) ABC analysis by annual dollar…
A: ABC analysis, also known as ABC classification, is a strategic inventory management technique that…
Q: Rapallo Sneakers, Inc. sells a pair of LG sneakers for $42. Due to the recent fitness craze, these…
A: Eoq- Economic ordering quantity helps us to find the fixed ordering quantity that minimizes the…
Q: If 50 units of A are needed, how many units of F are needed? a. 200b. 300c. 150d. 400
A: The given problem is with a product structure tree. The given figure is a product structure tree…
Q: Once the project starts, Cumulative Budgeted Cost (CBC) will periodically be compared to the:…
A: The total amount of money allocated to be spent on a project up until a specific point in time is…
Q: Identify the challenges associated with CRM implementation and how to overcome them
A: Customer relationship management (CRM) software has become a very important tool for companies of…
Q: Prepare an Introduction using the below topic and research questions
A: Staff absenteeism, a multifaceted phenomenon prevalent in organizational settings, represents the…
Q: what are strategies that firms might employ to reduce the impact of the bullwhip effect.
A: The bullwhip effect refers to the amplification of demand variability as it travels upstream in a…
Q: Discuss the key components of a successful CRM implementation.
A: Customer Relationship Management (CRM) systems have become integral to businesses looking to enhance…
Q: 1 2.5 2 3 2.5 2 3 6 5 2 8 7 7 Find the shortest(min cost) path From Node 1 to Node 7. Possible…
A: Network Flow Models- Consist of a network of sources and destinations. These are represented with…
Q: Find the value of X in the following Flow Shop data consisting of 5 jobs which are to be processed…
A: Johnson's Rule is a sequencing method that is applicable to scheduling two workstations. According…
Q: You run a small grocery store and have the following fruits in storage: 1000 apples, 1500 oranges,…
A: The information provided is stated in the table below:Gift Set AGift Set BGift Set…
Q: Forecasting Methodology: Choose an appropriate demand forecasting method (e.g., qualitative,…
A: Requirement: Explaining the chosen method of forecast and its rationale. Assumption: Assume the…
Q: 1) Which term is a typical arrival contract term? A DAT B CIP C CPT D CIF 2) Which shipment clause…
A: International logistic management is the part of management that is concerned with the flow or…
Q: Examine using practical examples what must be considered from the client's perspective for…
A: Supply chain integration implies bringing together entities in the supply chain, especially through…
Q: What are the most important things to you during this negotiation process? In what ways would you be…
A: The objective of this question is to understand the key factors that are important during a…
Q: According to the article: “The extensive upgrades included building an on-site Stamping Plant, a…
A: Manufacturing process strategies include purposeful approaches and techniques used to streamline…
Q: Forecast sales for the 7th period. For leveling, use exponential smoothing 0.20 and moving average 3…
A: PeriodDemand167272368420570666768
Q: Lou's Bakery has established that JIT should be used for chocolate chips due to the high probability…
A: Average demand per week = 140 cupsAverage setup and processing time = 1/8 dayHolding capacity of…
Q: A work team is looking at a current product in the LUML catalog --- the L555X fixture. The L555X…
A: The scenario presented revolves around a strategic initiative within a company, LUML, to enhance the…
Q: Angle Iron (AI), Inc. just purchased a new angle bending machine for foundation bases of their…
A: 1. Revenue for first two years is 3000 beams * 100 per beam= $300,000 Revenue for next 8 years is…
Q: According to the article, “The new and upgraded facilities were essential to unlock the plant’s…
A: Note:Since you have posted a question with multiple sub parts, we will provide the…
Q: asseterre, St. Kitts, April 29, 2021 (SKNIS): St. Kitts and Nevis Youth Ambassador Corps officially…
A: A stakeholder communication plan is an aspect that deals with managing and maintaining effective…
Q: Suzuki is a company that manufactures motorcycles. It produces 450 motorcycles a month. It buys…
A: Company produces = 450 motorcycles a month, Each motorcycle has two tires,So, the annual demand (D)…
Q: A local project being analyzed by PERT has 42 activities, 13 of which are on the critical path. If…
A: Given:Critical path duration (mu) = 105Variance (v) = 25New duration (x) = 95
Q: Use Holt-Winter’s multiplicative method to create a seasonal model that minimizes the MSE for the…
A: Holt-Winter’s additive method is a forecasting technique that considers both trend and seasonality.…
Q: The manufacturer of children’s toys designed a special toy truck that can be assembled in 8 basic…
A: Line balancing helps to find the optimal allotment of tasks to each workstation so that efficiency…
Q: A bakery buys sugar in 15-pound bags. The bakery uses 5000 bags of sugar each year. Carrying costs…
A: Maximum inventory is the most items or resources that a company or organization can keep on hand at…
Q: Create the following: • How do to inventory in supplies? • Seasonal Buildups? • Lead time for…
A: The methodical management and oversight of a business's products and supplies is known as inventory…
Q: Consider the following network representation of a transportation problem. 60 30 Jefferson City…
A: Find the given details below:
Q: a. b. C. d. Calculate simple average for the entire sales. Calculate 3-months moving average.…
A: MonthSalesJan4900Feb5000Mar5500Apr5200May5100Jun5600
Q: Regarding competency assessment, what are the strengths and weaknesses of the different assessments
A: With the help of competency assessment tools, we can specify and measure the skill levels,…
Q: Explain how Cp and Cpk relate and how they differ?
A: The question belongs to the field of statistical process control (SPC) and quality management, often…
Q: VOOM has four warehouses 1, 2,3, and 4. VOOM needs to supply 200 Tons to Retailer P, 200 Tons to…
A: For this question, I will prepare the spreadsheet model, Then, I will solve this spreadsheet model…
Q: Fairphone launched its first crowd- funded, ethically sourced, and envi- ronmentally conscious…
A: Business ethics is the aspects of business that define the standards or directives that assist in…
Q: 1. Diesel is leaking from the ship onto the dock. Answer (circle one): interpretation sharing,…
A: Communication is the aspect or part of the organization that includes sharing information, ideas,…
Q: Kilmer Company's customer demand for its only product exceeds its manufacturing capacity. The…
A: Let's break down steps one by one:1.a Utilization RateUtilization Rate=Actual Run Time/Machine Time…
Q: As the production planner for Xiangling Hu Products, Inc., you have been given a bill of material…
A: A product structure is a visual representation of material requirement plan which considering the…
Q: Critically discuss the various total quality management principles, practices and techniques that…
A: Total Quality Management (TQM) is a comprehensive approach that focuses on improving the quality and…
Q: What is the Available-to-Promise (ATP) for week 2? (A)
A: ATP (available to promise) is that portion of inventory or stock which is uncommitted. It helps in…
Q: Consider the assembly line below. The three fabrication operations run in parallel, such that each…
A:
Step by step
Solved in 4 steps with 4 images
- 1/ Katie Posh runs an upscale nail salon. The service process includes five activities that are conducted in the sequence described below. (The time required for each activity is shown in parentheses):Activity 1: Welcome a guest. (1 minute)Activity 2: Clip and file nails. (3 minutes)Activity 3: Paint. (5 minutes)Activity 4: Dry. (10 minutes)Activity 5: Check out the customer. (4 minutes)Three servers (S1, S2, and S3) offer the services in a worker-paced line. The assignment of tasks to servers is the following: S1 does Activity 1. S2 does Activities 2 and 3. S3 does Activities 4 and 5. The drying process does not require server 3’s constant attention; she/he needs to only escort the customer to the salon’s drying chair (equipped with fans for drying). The time to do this is negligible. There exists only one drying chair in the salon.a. What is the utilization of server 2 (in decimal form)? Assume that there is unlimited demand and that the process only admits customers at the rate of…At an auto shop, six jobs are currently in queue. Job A B C D E F Arrival order 1 2 3 4 5 6 Processing time (minutes) 33 27 36 28 21 23 Using the shortest processing time scheduling approach, what is the average inventory of jobs in the system? Assume that processing of jobs will start immediately. Note: Round your answer to 2 decimal places.Joe's Twenty-four Seven Laundromat has the following jobs waiting to be processed. The first step of the process includes washing and drying the clothes; the second step is pressing the clothing. Joe wants to minimize the amount of time it takes to do all the jobs. The five jobs waiting to be processed are shown here. Job Wash andDry (hours) Press(hours) A 5 4 B 3 4 C 2 3 D 7 5 E 4 2 Wash and Dry Using FCFS, assume the jobs arrive in the order shown (A, then B, then C, etc.). Show the beginning time for each job and ending time for the whole process adding hours throughout the process. A -0 number of hours B-5 number of hours C-8 number of hours D-10 number of hours E-17 number of hours A B C D E 0 enter a number of hours enter a number of hours enter a number of hours enter a number of hours enter a number of hours enter a number of hours Press
- Five jobs are waiting for processing through two work centers. Their processing time (in minutes) at each work center is contained in the table below. Each job requires work center Alpha before work center Beta. According to Johnson's rule, which job should be scheduled first in the sequence? O A. V OB. U O C. R OD. S O E. T Job R S T Alpha 20 23 50 26 55 Beta 34 35 20 26 75AssumMe a customer orders a product online. SupPpose that the product is delivered later in the weEek. The time between the order placement and order delivery is known as: a. waitT time b. queue time c. cycle time d. process timeDiablo Electronics manufactures four unique products (A, B, C, and D) that are fabricated and assembledin five different workstations (V, W, X, Y, and Z) using a small batch process. Each workstation is staffedby a worker who is dedicated to work a single shift per day at an assigned workstation. Batch setuptimes have been reduced to such an extent that they can be considered negligible. A flowchart denotesthe path each product follows through the manufacturing process as shown in Figure 5.2, where eachproduct’s price, demand per week, and processing times per unit are indicated as well. Inverted trianglesrepresent purchased parts and raw materials consumed per unit at different workstations. Diablo canmake and sell up to the limit of its demand per week, and no penalties are incurred for not being able tomeet all the demand.Which of the five workstations (V, W, X, Y, or Z) has the highest utilization, and thus serves as the bottle-neck for Diablo Electronics?
- Five jobs are waiting for processing through two work centers. Their processing time (in minutes) at each work center is contained in the table below. Each job requires work center Sigma before work center Delta. According to Johnson's rule, what sequence of jobs will minimize the completion time for all jobs? Job Sigma Delta R 20 10 S 25 30 T 30 20 U 35 35 V 15 25 Part 2 A. V−S−U−T−R B. V−R−U−S−T C. R−V−T−S−U D. S−U−T−V−R E. R−S−T−U−VTo control queue and make deadlines, two things are essential: must schedule and plan carefully , what are these ?Consider a workstation that has one maintenance mechanic to repair failed machines. We can think of the mechanic as the processor (scarce resource) and the machines awaiting repair as the jobs. Let us assume that six machines are down, with estimated repair times given here, and that no new machines fail. 1 2 3 Job (fix machine #) Processing time 10 (hours) Job 1 2 3 4 5 6 2 Compute the flow time for each job using both the FCFS rule and the SPT rule, and compare the average flow times. Round your answers for average values to the nearest whole number. FCFS Rule 9 Flow Time (hours) Average flow time (FCFS rule): 4 5 6 1 8 6 hours
- state whether or not each situation would be considered “compensable time” (and why or why not). An employee of a fast food chain has to arrive at work 15 minutes early to change into the“mascot” costume and it typically takes another 15 minutes at the end of the shift to change outof the costume and properly store it. Due to the cost of the costume, employees are notallowed to take the costume home. The “mascots” typically work from 10am – 2pm, to coverthe lunch rush periods. How much time would be “compensable” for the mascots, assumingthe conditions/schedule listed above?2) George is a Radiology Technician at a local hospital and when on call, is required to be nofurther than 30 minutes away from the facility. Is the “on call” time, compensable?Calculate the Critical Ratios (CR): (Enter all responses rounded to two decimal places.) The following 5 overhaul jobs are waiting to be processed at Avianic's Engine Repair Inc. These jobs were logged as they arrived. All dates are specified as planning calendar days. Job CR 103 Job Due Date Duration (days) 103 214 10 205 223 7 309 217 11 412 219 5 517 217 15 Assume that all jobs arrived on day 180; today's date is 200.Calculate the Critical Ratios (CR): (Enter all responses rounded to two decimal places.) The following jobs are waiting to be processed at Jeremy LaMontagne's machine center. Today is day 245. Job Date Job Received Due Date Duration (days) 1 215 300 30 2 230 310 25 3 228 290 35 4 235 305 40 5 245 315 45