. What is the workstation cycle time? Workstation cycle time 80 seconds per unit . Balance this line using the largest number of following tasks. Use the longest task time as a secondary criterion. (Leave no cells blank - be certain to enter "0" wherever required.) Work Station I II Task A-B-E D Idle Time 이 20

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Problem 8-6 (Algo)
The desired daily output for an assembly line is 540 units. This assembly line will operate 720 minutes per day. The following table
contains information on this product's task times and precedence relationships:
TASK
A
B
с
D
E
F
H
TASK TIME
(SECONDS)
48
30
40
68
18
28
35
18
Work Station
I
||
III
IV
b. What is the workstation cycle time?
Efficiency
Workstation cycle time 80 seconds per unit
IMMEDIATE
PREDECESSOR
c. Balance this line using the largest number of following tasks. Use the longest task time as a secondary criterion. (Leave no cells
blank - be certain to enter "0" wherever required.)
Task
A
A
A-B-E
D
C-G
F-H
B
B
с
E-D
F-G
77.0 %
Idle Time
d. What is the efficiency of your line balance? (Round your answer to 1 decimal place.)
0
20
5
50
Transcribed Image Text:Problem 8-6 (Algo) The desired daily output for an assembly line is 540 units. This assembly line will operate 720 minutes per day. The following table contains information on this product's task times and precedence relationships: TASK A B с D E F H TASK TIME (SECONDS) 48 30 40 68 18 28 35 18 Work Station I || III IV b. What is the workstation cycle time? Efficiency Workstation cycle time 80 seconds per unit IMMEDIATE PREDECESSOR c. Balance this line using the largest number of following tasks. Use the longest task time as a secondary criterion. (Leave no cells blank - be certain to enter "0" wherever required.) Task A A A-B-E D C-G F-H B B с E-D F-G 77.0 % Idle Time d. What is the efficiency of your line balance? (Round your answer to 1 decimal place.) 0 20 5 50
Expert Solution
steps

Step by step

Solved in 5 steps with 5 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.