A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed. The daily demand is 100 toys. Times of the tasks are 2.73, 2.01, 2.13, 2.0, 2.61, 2.71, and 2.95 minutes for A, B, C, D, E, F, and G, respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task A does not need any predecessors; task B requires task A to be completed. To start task C and task D, each require task B to be completed. Task C must be completed prior to stating task E. Task F needs both task D and task E to be completed. Finally, task G can start only once task F is completed.Given we apply the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first, What will the estimated idle time in minutes for SECOND workstation? O a. 1.85 o b. None is the correct answer Oc 0.09 O d. 1.00 O e 0.06
Q: Canine Kernels Company (CKC) manufactures two different types of dog chew toys (A and B, sold in…
A: So, we have, Demand of product-A = 90 units per week Demand of product-B = 85 units per week Because…
Q: A work center consists of 4 machines working 8 hours a day for a 5-day week. If theutilization is…
A: Given data is Number of machines = 4 Working hours = 8hrs/day Working period = 5days/week…
Q: Based on the narrative given, identify SIX (6) weaknesses from the above payroll processes. For each…
A: Payroll processing refers to a crcuical business function, involving to decide on the net pay that…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Given- Available time per day = 8 hours × 60 minutes = 480…
Q: A business company has the following capacity per month
A: Introduction: The term Market refers to an exchange of goods and services between the buyer and the…
Q: What is the outcome when a bottleneck resource is augmented with more capacity? Throughput time…
A: Bottleneck resources refers to those resources which are available in equal or less ratio as…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Given Data: Task Time taken A 2.73 B 2.01 C 2.13 D 2.0 E 2.61…
Q: Illinois Furniture, Inc., produces all types of office furniture. The "Executive Secretary" is a…
A: Total duration during the day = 480 mins The average daily demand of chairs = 50 Desired output =…
Q: A heavy construction firm has been awarded contract to build a large concrete dam. It is expected…
A: effective cost = Cost − Salvage Value a) YEAR Remaining useful lifeat beginning of year SYD…
Q: c) What is the theoretical minimum number of workstations? d) Assign tasks to workstations. e) How…
A: In an assembly line, each task is assigned to a workstation in order to meet the specified…
Q: A product is completed when 18 tasks are done. These tasks are assigned to 6 workstations (each…
A: From the beginning of the first task to the finish of the last task, cycle time is the amount of…
Q: a machine installation job can be finished by 40 men in 40 days. how long will it take for 50 men to…
A: The details are as under 40 men complete installation in 40 days Time required by 50 men if work…
Q: Tailwind, Inc., produces high-quality but expensive training shoes for nmners. The Tailwind shoe,…
A: Activity Immediate Predecessors Duration A - 1 B A 3 C B 2 D B 4…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Required cycle time = Available time / No. of units to produce =…
Q: snip
A: Given that: Operating Time = 4 hours Production = 1500 units
Q: snip
A: a. The cycle time is 30 seconds. So, 1 phone comes out every 30 seconds. So, 1200 phones will take…
Q: XYZ Company produces and sells 2 products, Lambda and Gamma, and the production process goes through…
A: a) Plantwide traditional approach: applied rate = Estimated m/o cost/Estimated DLH applied…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Given Data: Task Time taken A 2.73 B 2.01 C 2.13 D 2.0 E 2.61…
Q: An existing facility is to be re-designed to produce electric ovens. The old machines in the…
A: d. Continuous: Through the deployment of a continuous improvement programme, waste motion, lost…
Q: evelop a solution for the following line balancing problem, allowing a cycle time of 5 minutes.…
A: The Precedence Diagram given below: A D F B C…
Q: What types of scheduling decisions are management likely to encounter in the following operations?…
A: Scheduling is a process decision that tries to offer the right mix of labor & machines to…
Q: Mike’s Auto Body Shop has five cars waiting to be repaired. The shop is quite small, so only one car…
A: Tardiness = Repairing time - Promising time Average tardiness = Total tardinessnumber of cars 1.…
Q: Georgetown Pizza makes favorite pan pizzas every day with three working shifts around the clock. The…
A: Break-Even Point - By measuring the market pricing to its actual amount, the breakeven point…
Q: The Pullman Mfg., Inc. three-station work cell illustrated in the figure below has two machines at…
A: Note: - As we can answer only three subparts and you have not specified which three need to answer,…
Q: In a job shop, effective capacity is only 43 percent of design capacity, and actual output is 71…
A: This is Operations Management question, here, given information are as stated below: Actual output…
Q: An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the totaltime…
A: Minimum cycle time = length of the longest task Therefore, the minimum cycle time = 2.4 minutes
Q: Mega Corp. is designing a product layout for a new electronic product. They plan to use this…
A: Any electrical equipment, appliance, material, system, or apparatus that conveys or is controlled by…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: The answer is below:
Q: The theoretical minimum number of workstations is ??? Were you able to assign all the tasks to the…
A: Line balancing refers to a strategy of production involving the balancing of machine time and…
Q: Georgetown Pizza makes its favorite pan pizzas every day with three working shifts around the clock.…
A: The question is related to Break Even Point. Break even point is that level of sales at which there…
Q: A set of tools costs Php 1,800 and can be ground twenty times. Each regrinding costs Php 18.00 and…
A:
Q: Sue Helms Appliances wants to establish an assem-bly line to manufacture its new product, the Micro…
A: Given information Activity Duration Immediate predecessors A 10 B 12 A C 8 A, B D…
Q: If a manager would like to have four workstations in a meat-processing plant. If the processing…
A: Below is the solution:-
Q: Data warehouse and OLAP; business intelligence (BI) solutions for end users Prepare a report for top…
A: In figuring, an information distribution center (DW or DWH), otherwise called a venture information…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Given Data: Task Time taken A 2.73 B 2.01 C 2.13 D 2.0 E 2.61…
Q: Positively Rivet Inc. is a small machine shop that produces sheet metal products. It had one line…
A: Performance bottlenecks can lead a generally utilitarian PC or worker to dial back to a slither. The…
Q: b) Given the demand, the cycle time for the production of the new train set =
A: Formula for cycle time : Cycle time = (Total time for work)/(Demand) Given, Demand = 4600 units…
Q: Discuss the difference between resource loading and resource leveling, and provide an example of…
A: Resource Loading is the allocation of the right resources to right set of tasks at the right time.…
Q: A manufacturer needs to produce 300 coffee pots per 8 hour day. The discrete tasks required to…
A:
Q: The Neptune’s Den Machine Shop specializes in overhauling outboard marine engines. Some engines…
A: SPT and EDD are the job sequencing rule in operation management which stands for shortest processing…
Q: In a job shop, effective capacity is only 88 percent of design capacity, and actual output is 69…
A: Design capacity can be referred to as the maximum production rate that can be utilized from…
Q: Create a simple but realistic S-curve showing the budget and time allotment for renovating a room,…
A: To renovate the room, first, I would identify the tasks, for each task, I would allocate a time data…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A:
Q: What is the outcome when a bottleneck resources is augmented with more capacity? Will throughput…
A: The assets that need a lot of time working in the supply chain for a particular demand are…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Given Data: Task Time taken A 2.73 B 2.01 C 2.13 D 2.0 E 2.61…
Q: • A producer of inkjet printers is planning to add a new line of printers, and you have been asked…
A: 1) Predecessor Diagram
Q: Workstation W Workstation X Workstation Y , with a total load time of ____ minutes. (Enter your…
A: Demand for each product is given. Demand for product A = 80 Units/ week Demand for product B = 75…
Q: A facility has a maximum capacity of 4,000 units per day using overtime and skipping the daily…
A: Capacity utilization rate is a measure of a company's performance on the basis of how close it has…
Q: Explain why doubling the capacity of a bottleneck may not double the system capacity? Use a…
A: Answer: The limiting factor or a constraint is considered to be a 'Bottleneck' in a workstation…
Q: Balancing a production line includes the following tasks, EXCEPT: Finding a cycle time in which each…
A: Production line balancing- it is the arrangement of the appropriate quantity of laborers and tools…
Step by step
Solved in 2 steps with 1 images
- A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed . The daily demand is 100 toys . Times of the tasks are 2.73,2.01 ,2.13,2.0,2.61,2.71 and 2.95 minutes for A,B,C,D,E,F, and G, respectively . However , due to the nature of the product there are precedencerules that must be observed . Such that Task A does not need any predecessors ; task B requires task A to becompleted . To start task C and task Deach require task B to be completed . Task must be completed prior to stating task E. Task F needs both task and task E to be completed . Finally , task G can start only once task F is completed . Given we apply the most remaining tasks rule for balancing the assembly line , with ties broken according to longesttask time first , the tasks that will be assigned to the THIRD workstation are a. D and F b . None is the correct answer c. D only d. E only e. B, C , and DA local toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed. The daily demand is 100 toys. Times of the tasks are 2.73, 2.01, 2.13, 2.0, 261, 2.71, and 2.95 minutes for A, B, C, D, E, F, and G, respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task A does not need any predecessors; task B requires task A to be completed. To start task Cand task D, each require task B to be completed. Task C must be completed prior to stating task E. Task F needs both task D and task E to be completed. Finally, task G can start only once task F is completed. What is the minimum number of workstations needed? O a. None of them O b. 8 O c. 4 d. 2 Oe. e to searchA local toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed. The daily demand is 100 toys. Times of the tasks are 2.73, 2.01, 2.13, 2.0, 2.61, 2.71, and 2.95 minutes for A, B, C, D, E, F, and G, respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task A does not need any predecessors; task B requires task A to be completed. To start task C and task D, each require task B to be completed. Task C must be completed prior to stating task E. Task F needs both task D and task E to be completed. Finally, task G can start only once task F is completed.Given we apply the most remaining tasks rule for balancing the assembly line, with ties broken according ?to longest task time first, What will the estimated idle time in minutes for FIRST workstation 0.06 .a O None is the correct anser .b O 0.09 .c O 1.00 .d O 1.85 .e O ace 近
- A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed. The daily demand is 100 toys. Times of the tasks are 2.73, 2.01, 2.13, 2.0, 2.61, 2.71, and 2.95 minutes for A, B, C, D, E, F, and G, respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task A does not need any predecessors; task B requires task A to be completed. To start task C and task D, each require task B to be completed. Task C must be completed prior to stating task E. Task F needs both task D and task E to be completed. Finally, task G can start only once task F is completed.What should be the calculated cycle time in minutes? O a. 0.9 O b. 4.4 O c. None is correct O d. 4.5 O e. 4.8 US PAGE NEXT PAGE MacBA local toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed. The daily demand is 100 toys. Times of the tasks are 2.73, 2.01, 2.13, 2.0, 2.61, 2.71, and 2.95 minutes for A, B, C, D, E, F, and G, respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task A does not need any predecessors; task B requires task A to be completed. To start task C and task D, each require task B to be completed. Task C must be completed prior to stating task E. Task F needs both task D and task E to be completed. Finally, task G can start only once task F is completed. Given we apply the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first, What will the estimated idle time in minutes for FOURTH workstation? O a. 0.06 O b. None is the correct answer О с. 1.85 O d. 1.00 e. 0.09A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed. The daily demand is 100 toys. Times of the tasks are 2.73, 2.01, 2.13, 2.0, 2.61, 2.71, and 2.95 minutes for A, B, C, D, E, F, and G, respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task A does not need any predecessors; task B requires task A to be completed. To start task C and task D, each require task B to be completed. Task C must be completed prior to stating task E. Task F needs both task D and task E to be completed. Finally, task G can start only once task F is completed. Given we apply the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first, What will the estimated idle time in minutes for THIRD workstation? O a. 1.00 O b. 0.06 O c. None is the correct answer O d. 1.85 e. 0.09
- A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed. The daily demand is 100 toys. Times of the tasks are 2.73, 2.01, 2.13, 2.0, 2.61, 2.71, and 2.95 minutes for A, B, C, D, E, F, and G, respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task A does not need any predecessors; task B requires task A to be completed. To start task Cand task D, each require task B to be completed. Task C must be completed prior to stating task E. Task Fneeds both taskD and task E to be completed. Finally, task G can start only once task F is completed. Given we apply the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first, What will the estimated idle time in minutes for SECOND workstation? Oa. None is the correct answer O b. 0.09 Oc 1.85 O d. 1.00 O e. 0.06A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed. The daily demand is 100 toys. Times of the tasks are 2.73, 2.01, 2.13, 2.0, 2.61, 2.71, and 2.95 minutes for A, B, C, D, E, F, and G, respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task A does not need any predecessors; task B requires task A to be completed. To start task C and task D, each require task B to be completed. Task C must be completed prior to stating task E. Task F needs both task D and task E to be completed. Finally, task G can start only once task F is completed. Given we apply the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first, the tasks that will be assigned to the THIRD workstation are O a. E only O b. D and F OC. B, C, and D d. None is the correct answer O e. D onlyA local toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed. The daily demand is 100 toys. Times of the tasks are 2.73, 2.01,2.13, 2.0, 2.61,2.71, and 2.95 minutes for A, B, C, D, E, F, and G, respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task A does not need any predecessors; task B requires task A to be completed. To start task C and task D, each require task B to be completed. Task C must be completed prior to stating task E. Task F needs both task D and task E to be completed. Finally, task G can start only once task F is completed.Given we apply the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first, the tasks that will be assigned to the THIRD workstation are О a. В. С, and D O b. Donly Oc Eonly O d. Dand F None is the correct answer
- A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed. The daily demand is 100 toys. Times of the tasks are 2.73, 2.01, 2.13, 2.0, 2.61, 2.71, and 2.95 minutes for A, B, C, D, E, F, and G, respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task A does not need any predecessors; task B requires task A to be completed. To start task C and task D, each require task B to be completed. Task C must be completed prior to stating task E. Task F needs both task D and task E to be completed. Finally, task G can start only once task F is completed.Given we apply the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first, the tasks that will be assigned to the SECOND workstation are, O a. Conly b. None is the correct answer O c. Cand E O d. Eonly O e. A, B, and CA local toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed. The daily demand is 100 toys. Times of the tasks are 2.73, 2.01, 2.13, 2.0, 2.61, 2.71, and 2.95 minutes for A, B, C, D, E, F, and G, respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task A does not need any predecessors; task B requires task A to be completed. To start task C and task D, each require task B to be completed. Task C must be completed prior to stating task E. Task F needs both task D and task E to be completed. Finally, task G can start only once task F is completed. Given we apply the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first, the tasks that will be assigned to the THIRD workstation are O a. E only O b. Dand F O c. None is the correct answer O d. B, C, and D O e. DonlyA local toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed. The daily demand is 100 toys. Times of the tasks are 2.73, 2.01, 2.13, 2.0, 2.61, 2.71, and 2.95 minutes for A, B, C, D, E, F, and G, respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task A does not need any predecessors; task Brequires task A to be completed. To start task C and task D, each require task B to be completed. Task C must be completed prior to stating task E. Task F needs both task D and task E to be completed. Finally, task G can start only once task F is completed.Given we apply the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first, the tasks that will be assigned to the SECOND workstation are O a. E only O b. None is the correct answer O c. Conly O d. CandE O e. A, B, and C NEXT PAGE IOUS PAGE