A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 60 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally starting task G needed, task F to be completed. The processing times for tasks, A. B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. What should be the cycle time in minutes? O a. 8.66 O b. 4.7 O c. None is the correct answer O d. 0.9 O e. 8.0
Q: At the campus copy shop, six jobs have arrived in the order shown (A, B, C, D, E, and F) at the…
A: Given data: Job Due time Duration A 8 1.85 B 4.5 0.25 C 6.5 1.2 D 7 1.55 E 6 1.3 F…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Cycle time is the actual total time incurred in manufacturing a product by the team members in an…
Q: Sunny Park Tailors has been asked to make three different types of wedding suits for separate…
A: First come first serve (FCFS) scheduling calculation just timetables the positions as per their…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Given table; Task Performance Time(Min) A 2.4 B 2.2 C 0.9 D 1 E 1.2 F 1.8 G 1.5…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Demand is the total quantity of goods and services for which the consumers are ready to pay…
Q: a. Determine the number of followers for each task. (Please answer number of tasks following…
A: Assigning each task to a workstation within an assembly line to fulfill the necessary production…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Demand is the total quantity of goods and services for which the consumers are ready to pay…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: This problem can be solved using: Cycle time = Available time / Desired output
Q: snip
A: Given that: Task duration of A: 1 day Task duration of B: 1 day Task duration of C: 1 day Task…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Production time= 8*60= 480 minutes Demand= 100 units Cycle time= production time/ demand= 480/100=…
Q: The Mowry Machine Shop still has five jobs to be processed as of 8 A.M. today (day 23) at its…
A: Given - Job Time Since Order Arrived(days ago) Processing Time (days) Due Date (days…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: This problem can be solved using:Cycle time = Available time / Desired output
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Given table; Task Performance Time(Min) A 2.8 B 2.1 C 0.9 D 1 E 1.2 F 1.8 G 4.7…
Q: Six jobs are to be processed through a two-step opera- tion. The first operation involves sanding,…
A: JOB OPERATION 1 (HOURS) OPERATION 2 (HOURS) A 10 5 B 7 4 C 5 7 D…
Q: At the campus copy shop, six jobs have arrived in the order shown (A, B, C, D, E, and F) at the…
A: note: since only d and e are asked, the same are being answered. Given data: Job Due time…
Q: As a production supervisor, Joe decides on Friday afternoon how many units of output his employees…
A: Controlling - Controlling is a role of management that supports to check faults in command to take…
Q: The Earliest Due date (EDD) rule for sequencing a given set of jobs usually ____________ Select…
A: Scheduling is a technique for allocating precious computational resources typically processor time,…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A:
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: This problem can be solved using: Minimum no. of station = Total task time / Cycle time Cycle time =…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: This problem can be solved using: Minimum no. of station = Total task time / Cycle time Cycle time =…
Q: A merchant wants to cut a group of pieces of cloth, each of more than 5 meters long, into small…
A: A map of operations is the visual description of the workflow of a project which describes the…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: This problem can be solved using: Minimum no. of station = Total task time / Cycle time Cycle time =…
Q: in an assignment problem involving 8 workers and 8 jobs, total number of assignments possible are…
A: One of the properties of assignment problems is that only one job can be assigned to a worker. So,…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Cycle time is 15.14 minutes
Q: Using the assembly-line balancing procedure, which of the following is the theoretical minimum…
A: Below is the solution:-
Q: A production line is to be designed for a job with three tasks. The task times are 0.3 minutes, 1.4…
A: Answer: In this mentioned problem, a job has three elemental tasks. Cycle time is the maximum amount…
Q: Sunny Park Tailors has been asked to make three different types of wedding suits for separate…
A: Given, SUIT CUT AND SEW DELIVER 1 7 2 2 4 3 3 5 6
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Demand is the total quantity of goods and services for which the consumers are ready to pay…
Q: In a school, there are four teachers X1,X2,X3,X4 and five batches Y1,Y2,Y3,Y4,Y5. Given that teacher…
A: The given question is of an unbalanced minimization problem of assignment. In order to slove the…
Q: Homework help starts here! ASK AN EXPERT CHAT MATH SOLVER Question Question A business is…
A: Given data is
Q: Task 6 is done by Select an answer starting at time Task 7 is done by Select an answer v starting at…
A: The answer is as below:
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Demand is the total quantity of goods and services for which the consumers are ready to pay…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Cycle time is the total actual time spend to produce an item in the production process.
Q: The Mowry Machine Shop still has five jobs to be processed as of 8 A.M. today (day 23) at its…
A: Given, Job Time Since Order Arrived (days ago) Processing Time (days) Due Date…
Q: Six jobs are to be processed through a two-step operation. The first operation involves sanding, and…
A: In operations, Johnson's rule is a technique of scheduling jobs in two work centers. Its primary…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Total Working hours=8 hour or 480 minutes Total Task =7 task Daily Demand= 120 toys Total task time…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: This problem can be solved using: Cycle time = Available time / Desired output
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: This problem can be solved using: Minimum no. of station = Total task time / Cycle time Cycle time =…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and producesa toy that…
A: Production is the process of manufacturing the finished products and services using raw materials…
Q: A nursing home must schedule nurses in a manner that balances providing adequate patient care while…
A: Given data, Shift Time Minimum number of nurses 1 12 am -4 10 2 4 am- 8 6 3 8 am -12 8…
Q: Three jobs are to be scheduled on two machines A and B. Assume that the jobs are processed in the…
A: GIVEN,
Q: Jse the given tasks and predecessors for this problem. The required cycle time is 25 seconds and…
A: None, Workstation 1 should only have task A assigned
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Cycle time = Total Available time Desired Output
Q: A group of six jobs is to be processed through a two-machine flow shop. The first operation involves…
A:
Q: Six jobs are to be processed through a two-stepoperation. The first operation involves sanding, and…
A: Optimal sequence: E D C A B F
Q: Question: Balance this line using the longest task time heuristic.
A: The longest-time heuristic method ensures that the most difficult tasks to fit into a station are…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: This problem can be solved using:Cycle time = Available time / Desired output
Step by step
Solved in 2 steps
- A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 90 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C D E F and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed, Starting tasks needs the task to be completed. Also starting task D, needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F. and G are 28.2.1,0.9, 10, 1.2.1.8 are 4.7 minutes respectively. How many minimum numbers of workstations are needed? a. 1 b. 6 c. None is correct d. 3 e. 5 please I neef answer along with the formula don't put it on excelA manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 70 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F. and Grespectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, and 4.7 minutes respectively. What should be the cycle time in minutes? O a. 4.4 O b. 7.5 O c. 4.7 O d. 6.86 e. None is the correct answerA manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 80 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and Gare 2.8, 2.1,0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. How many minimum numbers of workstations are needed? Select one: a. None is the correct answer b. 5 C. 6 d. 3 e. 1
- A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 110 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and Grespectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, and 4.7 minutes respectively. How many minimum numbers of workstations are needed? O a. 1 Ob. 2 c. 6. O d. None is the correct answer O e. 4 82°F Mostly cle acerA manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 110 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and Grespectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting taskGneeded, task Fto be completed. The processing times for tasks, A, B, C. D, E, F, and Gare 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, and 4.7 minutes respectivelV How many minimum numbers of workstations are needed? None is the correct answer O b. 6 O c. 4 O d. 2 Oe. 1A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 150 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and Grespectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D. E, F, and Gare 2.3, 2.1,0.9, 1.0, 1.2, 1.8, and 1.5 minutes respectively. Applying the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first. What will be the idle time for the LAST Workstation? O a 14 Ob. 1.7 Oc. None is the…
- A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 180 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and Grespectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.4, 2.2, 0.9, 1.0, 1.2, 1.8, are 1.5 minutes respectively. Applying the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first. What is the idleness in percentage? a. 31.34 O b. 81.82 O c. None is the correct…A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 180 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and Grespectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks Dand E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A. B, C, D, E, F, and G are 2.4, 2.2, 0.9, 1.0, 1.2, 1.8, are 1.5 minutes respectively. Applying the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first. What will be the idle time for the FOURTH Workstation? O a. 0.57 O b. 1.67 O c. 0.47…A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 180 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and Grespectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only startupon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task Fto be completed. The processing times for tasks, A, B, C, D, E, F, and Gare 2.4, 2.2,0.9, 1.0, 1.2, 1.8. are 1.5 minutes respectively. How many minimum numbers of workstations are needed? Round-up to the nearest integer O a. 8 O b. 5 Oc. None is the correct answer O d. 6 O e. 4.
- A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 180 units per day. The product requires 7 tasks in total. These tasks are namely, A. B, C, D, E, F, and Grespectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only startupon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A. B, C, D, E, F, and G are 2.4, 2.2, 0.9, 1.0, 1.2, 1.8, are 1.5 minutes respectively. Applying the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first. What will be the idle time for the FIRST Workstation? O a. 0.47 O b. 0.27 Oc. 0.57 O…A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 150 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D. E. F. and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.3, 2.1, 0.9, 1.0, 1.2, 1.8, and 1.5 minutes respectively. Applying the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first. What will be the idle time for the FOURTH Workstation? O a. 1.0 O b. 1.4 C. 0.9 O…A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 90 units per day. The product requires 7 tasks in total. These tasks are namely, A. B, C, D. E,F. and Grespectively. Task A does not have any predecessor to start. To start Task B. it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C Whereas starting task F needs the completion of both the tasks Dand E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A. B. C. D. E.F. and Gare 2.8.21,0.9.1.0, 1.2. 1.8, and 4.7 minutes respectively. How many minimum numbers of workstations are needed? Oa 3 Ob. None is the correct answer Oc 5 Od. 1 Oe 6