A plastic-manufacturing company owns andoperates a polypropylene production facility that converts the propylene from one of its cracking facilitiesto polypropylene plastics for outside sale. The polypropylene production facility is currently forced tooperate at less than capacity due to an insufficiencyof propylene production capacity in its hydrocarboncracking facility. The chemical engineers are considering alternatives for supplying additional propyleneto the polypropylene production facility. Two feasiblealternatives are to build a pipeline to the nearest outside supply source and to provide additional propylene by truck from an outside source. The engineersalso gathered the following projected cost estimates.• Future costs for purchased propylene excludingdelivery: $0.215 per lb.• Cost of pipeline construction: $200,000 per pipeline mile.• Estimated length of pipeline: 180 miles.• Transportation costs by tank truck: $0.05 per lb,utilizing a common carrier.• Pipeline operating costs: $0.005 per lb, excludingcapital costs.• Projected additional propylene needs: 180 millionlb per year.• Projected project life: 20 years.• Estimated salvage value of the pipeline: 8% of theinstalled costs.Determine the propylene cost per pound under eachoption if the firm’s MARR is 18%. Which option ismore economical?

Cornerstones of Cost Management (Cornerstones Series)
4th Edition
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Don R. Hansen, Maryanne M. Mowen
Chapter19: Capital Investment
Section: Chapter Questions
Problem 24P
icon
Related questions
Question

A plastic-manufacturing company owns and
operates a polypropylene production facility that converts the propylene from one of its cracking facilities
to polypropylene plastics for outside sale. The polypropylene production facility is currently forced to
operate at less than capacity due to an insufficiency
of propylene production capacity in its hydrocarbon
cracking facility. The chemical engineers are considering alternatives for supplying additional propylene
to the polypropylene production facility. Two feasible
alternatives are to build a pipeline to the nearest outside supply source and to provide additional propylene by truck from an outside source. The engineers
also gathered the following projected cost estimates.
• Future costs for purchased propylene excluding
delivery: $0.215 per lb.
• Cost of pipeline construction: $200,000 per pipeline mile.
• Estimated length of pipeline: 180 miles.
• Transportation costs by tank truck: $0.05 per lb,
utilizing a common carrier.
• Pipeline operating costs: $0.005 per lb, excluding
capital costs.
• Projected additional propylene needs: 180 million
lb per year.
• Projected project life: 20 years.
• Estimated salvage value of the pipeline: 8% of the
installed costs.
Determine the propylene cost per pound under each
option if the firm’s MARR is 18%. Which option is
more economical?

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Internal Control Audit
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning