ABC Manufacturing is evaluating the desirability of implementing process improvements and is seeking your help in determining whether it should proceed with the proposed improvements. One area of focus is how the improvements will affect processing time (manufacturing cycle time efficiency). Estimated activities and associated times for these activities under both the current process and after process improvements are as follows: Process Activity Current Process After Process Improvements Wait time 4 hours 1 hour Inspection 40 minutes 5 minutes Moving 80 minutes 20 minutes Processing (manufacturing) 2 hours 75 minutes Required: 1. Determine the manufacturing (production) lead time (in minutes) for each of the two decision alternatives. 2. Determine the manufacturing cycle efficiency (MCE) for each decision alternative.
ABC Manufacturing is evaluating the desirability of implementing process improvements and is seeking your help in determining whether it should proceed with the proposed improvements. One area of focus is how the improvements will affect processing time (manufacturing cycle time efficiency). Estimated activities and associated times for these activities under both the current process and after process improvements are as follows: Process Activity Current Process After Process Improvements Wait time 4 hours 1 hour Inspection 40 minutes 5 minutes Moving 80 minutes 20 minutes Processing (manufacturing) 2 hours 75 minutes Required: 1. Determine the manufacturing (production) lead time (in minutes) for each of the two decision alternatives. 2. Determine the manufacturing cycle efficiency (MCE) for each decision alternative.
Chapter1: An Overview Of Strategic Marketing
Section1.2: Dollar Shave Club: The Company For Men
Problem 1C
Related questions
Question
ABC Manufacturing is evaluating the desirability of implementing process improvements and is seeking your help in determining whether it should proceed with the proposed improvements. One area of focus is how the improvements will affect processing time (manufacturing cycle time efficiency). Estimated activities and associated times for these activities under both the current process and after process improvements are as follows:
Process Activity | Current Process | After Process Improvements | ||
---|---|---|---|---|
Wait time | 4 | hours | 1 | hour |
Inspection | 40 | minutes | 5 | minutes |
Moving | 80 | minutes | 20 | minutes |
Processing (manufacturing) | 2 | hours | 75 | minutes |
Required:
1. Determine the manufacturing (production) lead time (in minutes) for each of the two decision alternatives.
2. Determine the manufacturing cycle efficiency (MCE) for each decision alternative.
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 1 images