An operatlons consultant for an automalic car wash wishes to plan for enough capacity co handle 60 cars per hour. Each car will nave wash time of 2 minutes, but there is to pe a 20 per centallowance for setup, delays end payment transactions. The installation
Q: Nadicorp workshop has the capacity to repair 800 busses per month. Due to the current trend change…
A: Here, I would determine the utilization, efficiency of the workshop, the design capacity of the…
Q: 6
A: Ans 1: Precedence graph of the given data
Q: CAPACITY ANALYSIS WITH SIMULTANEOUS PROCESSES Dr. Cynthia Knott’s dentistry practice has been…
A: Solution The flowchart of the process is shown below -
Q: If Proven Special Electric Motors require a total of 48 (5+12+11+4+16) minutes to assemble, demand…
A: Find the given details below: Given Details Assemble time for a motor 48 mins Demand 27.3…
Q: The Academic Computer Center has five trainers available in its computer labs to provide training…
A: Operational efficiency is described as the organizational ability to focus on the reduction of…
Q: The three-station work cell illustrated in Figure S7.7has a product that must go through one of the…
A: The bottleneck is the situation when inventory gets piled in between the process due to less…
Q: The Academic Computing Center has five trainers available in its computer labs to provide training…
A: Efficiency refers to the working capacity of an input. It is a measure that helps in determining the…
Q: The school cafeteria can make pizza for approximately $0.30 per slice. The cost of the kitchen use…
A: school cafeteria can make pizza for approximately $0.30 per slice. cost of the kitchen use and…
Q: What are some capacity measures for each of the following?a. Universityb. Hospitalc. Computer repair…
A: Capacity Measures:- Measures the amount of fluid that an article holds. For instance, the limit of a…
Q: Money Laundry has 22 washers and 34 dryers. All orders are first sent to wash and then to dry. It…
A: “Since you have posted a question with multiple sub-parts, we will solve the first three subparts…
Q: Explain how flexible capacity as per demand can be created in each of the following services a) A…
A: Flexible capacity means the additional production capacity that a company can adjust at the time by…
Q: The school cafeteria can make pizza for approximately$0.30 a slice. The cost of kitchen use and…
A: Formula:
Q: Amy Xia’s plant was designed to produce7,000 hammers per day but is limited to making 6,000…
A: Capacity utilization is a part of plant utilization. It means how much capacity the plant is and how…
Q: Several graduate students at ABC University formed a company called the ABC River Rafting Company to…
A: Initial investment $2,000 Labor and material cost $5 per raft
Q: Southeastern Oklahoma State University's businessprogram has the facilities and faculty to handle an…
A: Given; The actual intake is 1450 and the Design capacity is 2000.
Q: NorSal Trondheim operates a salmon processing facility where fish are purchased from local sources…
A: Note: - Since we answer up to 3 subparts, we will answer questions 1,2 and 3. Please resubmit the…
Q: Southeastern Airlines's daily flight from Atlanta to Charlotte uses a Boeing 737, with all-coach…
A:
Q: If a plant has an effective capacity of 6,500 andan efficiency of 88%, what is the actual (planned)…
A: A product is a tangible substance that is offered in the market to satisfy the desire or requirement…
Q: of hour. Two repaiment A and B have been interviewed. Repairman A charges Kshs & hour and services…
A: Given- For Repairman A-λ= 5 per hour, μ = 7 machine per hour, Labor cost = Kshs 8 per hour For…
Q: 1. PUP 48,213 UST 40,000 FEU 27,889 LRT2 200,000 passengers daily If 60% of PUP, 30% of UST, and 85%…
A: Given, PUP 48,213 UST 40,000 FEU 27,889 LRT2 200,000 passengers
Q: The school cafeteria can make pizza for approximately $0.30 per slice. The cost of the kitchen use…
A: Pizza's rate = $9 No. Of slices = 8 Per slice rate = 9/8 = $ 1.125 However the fixed cost per day is…
Q: Warehouse Management System Case The warehouse area of MFA Company is presently filled to capacity…
A: BELOW IS THE SOLUTION:-
Q: An university is planning to arrange an international conference with the capacity of 500…
A: The term capacity cushion can be understood as a capacity which a company has maintained separately…
Q: 4) Capacity Requirements Planning Abe is typically scheduled to operate 4 machines at his…
A: Since you have submitted multiple questions, we have answered the first question completely, for…
Q: Carry out a critical differentiation among the design capacity and effective capacity of capacity…
A: Design Capacities and Effective capacities are the two types of capacities which are studied under…
Q: The three-station work cell at Pullman Mfg., Inc.is illustrated in Figure S7.8. It has two machines…
A: The pacemakers of existing processes are bottlenecks in your process. Fixing the bottlenecks in your…
Q: Capacity Requirements Planning Abe is typically scheduled to operate 4 machines at his workstation…
A: Given information: Number of machines (n) = 4Number of hours worked per day (w) = 8 hoursNumber of…
Q: 29. The north-south highway system passing through Albany, New York, can accommodate the capacities…
A: The given question is about the maximal flow problem. Here, the maximum flow from the network is…
Q: Explain what exactly is capacity requirements planning?
A: Capacity requirement planning is the accounting term for the process of determining a company's…
Q: b. An employee has proposed adding new equipment that would speed up the loading rate to 5.71 trucks…
A: The rate of service in a firm is calculated by using the service rate, which is a performance…
Q: The Yankee Machine Shop currently has three machinesworking in Work Center 111, eight hours per day,…
A: It is given that the three machines are working eight hours a day, utikizing 90 percen efficency.
Q: What is the workstation utilization? Given an efficiency of 90%, what is the typical weekly…
A: In the above question: The number of machines is 4, the number of working hours is 8 and no of…
Q: Party Apparel Inc. has 20 operators and work 8 hours a day, 5 days a week. They specialize in making…
A: Answer = 5
Q: Discuss what is flexible facilities and multi skilled workforce in Just -In-Time (JIT)?
A: Flexible Facilities and Multi-Skilled Workforce As previously noted, organisations that produce the…
Q: Purple Swift manufactures birdhouses in lots of 10. Eachbirdhouse takes 45 minutes to paint. After…
A: Utilization = Average Output Rate / Maximum Capacity Utilization = [(Number of lots x Setup Time) +…
Q: Southeastern Oklahoma State University's business program has the facilities and faculty to handle…
A: Given data; Design capacity 2100 students/semester Effective capacity 1800 students/semester…
Q: Give 4 examples of factors that can reduce capacity momentarily.
A: Capacity Planning: The main objective of the capacity planning is to deliver the…
Q: Southeastern Oklahoma State University's business program has the facilities and faculty to handle…
A: Given, Design Capacity = 2100 Students Effective Capacity = 1800 Students Actual Output = 1420…
Q: What volume (units) of output would the two alternatives yield the same profit?…
A: Given data For proposal A Fixed cost = $50000 Variable cost = $12 Revenue = $20 For proposal B…
Q: The three-station work cell illustrated in Figure S7.7has a product that must go through one of the…
A: Note: As per the Bartleby guidelines only the first three parts have been answered. The cycle time…
Q: a. Determine the break-even point for each range. h. If estimated demand is 90 to 120 customers per…
A: The breakeven point is the level of production where the costs of production are equal to the…
Q: Explain Goldratt’s Theory of Constraints (TOC)?
A: Theory of Constraints (TOC) is the project management concept developed by Dr. Eliyahu M. Goldratt…
Q: Explain the importance of capacity planning in deciding on the no. Of police officers or fire trucks…
A: In simpler terms, supply chain can be characterized as workloads. It indicates that however much…
Step by step
Solved in 2 steps
- 9. Shouldice Hospital in Canada is widely known for one thing—hernia repair! In fact, that is the only operation it performs, and it performs a great many of them. Over the past two decades this small 90-bed hospital has averaged 7,000 operations annually. Last year, it had a record year and performed nearly 7,500 operations. A hernia repair operation at Shouldice Hospital is performed by one of the 12 full-time surgeons assisted by one of seven part-time assistant surgeons. The first operations begin at 7:30 AM each day, Monday through Friday. Surgeons generally take about one hour to prepare for and perform each hernia operation, and they operate on an average of at most four patients per day. This four patient per day limit on the average number of operations performed per surgeon has been found to be the best operating level for the hospital as it takes into account time the surgeons need for patient exams and consultations, updating medical charts, writing reports, traveling to…IIn a job shop, effective capacity is only 69 percent of design capacity, and actual output is 76 percent of effective output. What design capacity would be needed to achieve an actual output of 13 jobs per week? What is its effective capacity? a. The Design Capacity needed to achieve the required actual job outputs =Blank 1 (round to whole number) b. The Effective Capacity needed to achieve the required actual job outputs = Blank 2 (round to whole number) Blank 1 Blank 2 Add your answer Add your answerPlease do not give solution in image formate thanku During the early morning hours, customers arrive at a branch post office at an average rate of 57 per hour (Poisson), while clerks can provide services at a rate of 19 per hour. If clerk cost is $50.14 per hour and customer waiting time represents a cost of $46 per hour, how many clerks can be justified on a cost basis a. 8 b. 4 c. 7 d. 6 e. 5
- L. Winston Martin (an allergist) has an excellent system for handling his regular patientswho come in just for allergy injections. Patients arrive for an injection and i llout a name slip, which is then placed in an open slot that passes into another roomstaffed by one or two nurses. The specii c injections for a patient are prepared, andthe patient is called through a speaker system into the room to receive the injection.At certain times during the day, patient load drops and only one nurse is needed toadminister the injections.Let’s focus on the simpler case of the two—namely, when there is one nurse. Also,assume that patients arrive in a Poisson fashion and the service rate of the nurse is exponentiallydistributed. During this slower period, patients arrive with an interarrival time ofapproximately three minutes. It takes the nurse an average of two minutes to prepare thepatients’ serum and administer the injection.a. What is the average number you would expect to see in Dr.…A milling department has 10 machines. Each operates an average of eight hours before requiring adjustment, which takes an average of 3.43 hours. While running, each machine can produce 50 pieces an hour. Use Table 1, Table 2 and Table 3. a. With one adjuster, what is the net average hourly output per machine? (Round your answer to 1 decimal place.) Number of Pieces ?? per machine b. If machine downtime cost is $75 per hour and adjuster cost is $31 per hour, how many adjusters would be optimal? Multiple Choice 1 2 3 4 5Diagrams of two self-service gasoline stations, both locatedon corners, are shown in Figure 2.19(a) and (b). Both havetwo rows of four pumps and a booth at which an attendantreceives payment for the gasoline. At neither station is itnecessary for the customer to pay in advance. The exits andentrances are marked on the diagrams. Analyze the flows ofcars and people through each station.a. Which station has the more efficient flows from the standpoint of the customer?b. Which station is likely to lose more potential customerswho cannot gain access to the pumps because another caris headed in the other direction?c. At which station can a customer pay without getting out ofthe car?
- diference between design capacity and effective capacity with examplesSMART goals for Building Ethics Capacity across HospitalMelanie is the manager of the Clean Machine car washand has gathered the following information. Customers arriveat a rate of eight per hour according to a Poisson distribution.Th e car washer can service an average of ten cars per hour withservice times described by an exponential distribution. Melanie isconcerned about the number of customers waiting in line. She hasasked you to calculate the following system characteristics:(a) Average system utilization(b) Average number of customers in the system(c) Average number of customers waiting in line
- The manager of a car wash must decide whether to have one or two wash lines. One line will mean a fixed cost of $6,000 a month, and two lines will mean a fixed cost of $10,500 a month. Each line would be able to process 15 cars an hour. Variable costs will be $3 per car, and revenue will be $5.95 per car. The manager projects an average demand of between 14 and 18 cars anhour. Would you recommend one or two lines? The car wash is open 300 hours a month.er A product line includes 8 different product styles, each consisting of 93 components. Assume that 9 processing operations are needed to produce each component on average with each operation taking an average 1.2 min, which includes setup time and part handling time. All operations need a production machine, and currently 25 machines are dedicated to this task. The plant operates 52 hours per week, 52 weeks a year. Determine the yearly production of each style in units (round downward). 63 504With a 10% availability buffer, a contact centre has been handling 900 consumers per day. Customers have shown dissatisfaction with the amount of time it takes for their call to be replied. How much additional space is needed if the call centre manager wishes to double the capacity cushion?