b) The critical activities for the leadership training program development project are c) The project length for the leadership training program development project = days. d) Slack time for each of the activities is: Actiw
Q: Activity Immediate Predecessor(s) Time (days) 10 7 A, D 4 G E, F 10 This exercise contains only…
A: Forward Pass- Early Start (ES)= Maximum (or Highest) EF value from immediate Predecessor(s)…
Q: Q2: For the activities shown below determine: . The duration of project . The critical path by using…
A: ANSWER IS AS BELOW:
Q: c. Suppose that the indirect costs of the project amount to $200 per day. Find theoptimal number of…
A: Given Data Activity Immediate Predecessor Normal Time Expedited Time Normal Cost Expedited…
Q: B. What is the expected project completion time? 7 weeks 8 weeks 9 weeks 6 weeks C. Which are the…
A: In this question, I would construct the Gantt chart based on the given Activity ID, Activity…
Q: 1- Data for small project are given, determine the following 1- ES for Activity C. E. G. J 2- E.F…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: The new director of special events at a large university has decided to completely revamp graduation…
A: Given data is
Q: a) What are the activities on the critical path (using the letters provided) b) What is the shortest…
A: We are allowed to do first three sub-parts only. The answer is as below:
Q: Which of the following activities is not part of defining a project?a. The project triangleb. The…
A: An organization has numerous projects running at a time and numerous projects in the pipeline to be…
Q: 9.A Sample of EARNED VALUE ANALYSIS The following project is at the end of its 5 week.Find the cost…
A: NOTES: 1.0 CR = (actual progress/scheduled progress) x (budgeted cost/actual cost).…
Q: Which process involves measuring against the project schedule baseline by looking to see what things…
A: Project schedule A project schedule can be explained as a plan for completing a project…
Q: Solve the following project by hand and submit your notes: Activity Normal Time Crash Time Normal…
A: Please find the attached network diagram below-
Q: 15F - Estimate how long (total time in months from start to finish, not how many months remain -…
A: THE ANSWER IS AS BELOW:
Q: The following activities are part of a project to be scheduled using CPM: АсTIVITY IMMEDIATE…
A: This question is related to the topic - Project Management and this topic fall under the operations…
Q: Define a process in project management with the help of an example?
A: Project management: Project management is defined as it is a structured process of…
Q: a. Determine the expected activity completion times, te. b. Identify the critical path. c. What's…
A: The first four subparts (a), (b), (c), and (d) are answered below.
Q: a) Draw an AON diagram of the project, including activity durations. b) Define the critical path,…
A: In project management, there are two types of networks. One is AON and the second is AOA. AON…
Q: Suppose you have a project with a Budget at Completion (BAC) of $250,000 and a projected length of…
A: Given, Budget at Completion (BAC) of $250,000 Time- 10 months
Q: a. Determine the project completion time if no activity is crashed. What would be the total cost of…
A: Below is the solution:-
Q: Who creates the project schedule?
A: Project scheduling refers to creating a schedule containing the activities, milestones, and…
Q: The most critical responsibilities Anne has to marshal, schedule and manage on a daily basis are…
A: There are some resource which are to be considered during the life time of the project. Such project…
Q: The translates the needs of the organization through chartering the project and defining the project…
A: A project is a collection of tasks that must be accomplished in order to reach a specific objective…
Q: Construct a Gantt chart for the following set of activities and indicate the project completion…
A:
Q: m- the network diagram of one of the projects and its data as in Table No. (4), so if I want to…
A: Below is the solution:-
Q: 1. Determine the amount of slack in each of a project's activities (presented below), and identify…
A:
Q: Q4. Answer the following questions (a-h), based on the provided project Gantt Chart. The red line…
A: Note: Since you have posted a question with multiple sub-parts, we will solve first four sub-parts…
Q: Please help me with this question
A: Activity Immediate Predecessors Duration 1A - 6 1B 1A 2 1C 1A 2 1D…
Q: ) Construct an AON diagram using the above the Project Management table. ) What is the Critical Path…
A: The answer is as below:
Q: the working of the t
A: The triple constraint theory in project management states that undertaking works inside the limits…
Q: c) What is the critical path for this project and how long is it?
A: Below is the solution:-
Q: G This exercise contains only parts b, c, and d. b) The critical activities for the leadership…
A: The critical activities are the activities that lie on the critical path of a project. In a project,…
Q: A. (5 points) Draw AON diagram of the project, including activity durations. B. (4 points) Based on…
A:
Q: Identify the term being described for each of the following: b. The longest time sequence of…
A: b. The critical path is the longest time sequence of activities in a project.
Q: b) The activities on the critical path are c) The total project completion time for Rafay Ishfaq's…
A: THE ANSWER IS AS BELOW:
Q: Before answering the following questions, you must draw the arrow diagram, rectangles, network…
A: Forward Pass:Early Start (ES)= Maximum (or Highest) EF value from immediate Predecessor(s)Early…
Q: Based on the diagram in question 3, what happens to the project duration if Activity C is done at…
A: If Activity C is done at the same time as Activity D, then both the activities will done in 4 days…
Q: Below is the details about a. What is the maximum and minimum human resource that would be required…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: 1. Activities of a project are summarized in the following table. Activity Immediate Duration…
A: Hi, we are supposed to answer three subparts at a time. Since you have not mentioned which subpart…
Q: The following CPM/PERT network represents a small project with 4 activities labelled A through D.…
A: Given data is
Q: The fo llowing is a table of activities associated with a project at Rafay lshfaq's software firm in…
A: Note: As per the Bartleby guidelines only the first three parts have been answered. AOA ( Arrow to…
Q: 3. Draw a project network from the following information. What activity(s) is a burst activity? What…
A: A network diagram is the graphical representation of project activities or tasks and their duration…
Q: a) Draw the project network using AON. b) Identify the critical path. c) What is the expected…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Given the activities of a project, their time estimates, and their immediate predecessors shown…
A: Given information Activity Activity Time Immediate predecessors A 2 B 3 C 2 A D 4…
Q: Assess the planning, monitoring, and controlling of projects using the Program Evaluation and Review…
A: The Program Evaluation Review Technique (PERT) is a technique used in project management to…
Q: Calculate the ES, EF, LS, and LF times and the slack for each activity in t the critical path for…
A: The full form of the term is as follow, ES- Earliest Start Time EF-Earliest Finish Time LS-Latest…
Q: The network dlagram and task times for a project are shown below. A2 A4 A5 A3 Task Duration (days)…
A: Using Forward Path, find Early Start of the activity = Early Finish of predecessor activity Early…
Q: The data below represent a project that can be completed at normal cost in 15 days. The project can…
A: Find the Given details below: Activity Predecessor Normal Time (NT) (Days) Crash Time (CT) (Days)…
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 4 images
- Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) Time (days) A − 2 B − 6 C − 1 D B 10 E A, D 3 F C 6 G E, F 8 This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are ▼ C - F - G A - E - G B - D - E - G . c) The project length for the leadership training program development project = enter your response here days. d) Slack time for each of the activities is: Activity Slack Time A enter your response here B enter your response…Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) Time (days) A − 4 B − 6 C − 1 D B 10 E A, D 5 F C 5 G E, F 8 This exercise contains only parts b, c, and d. Part 2 b) The critical activities for the leadership training program development project are ▼ B - D - E - G C - F - G A - E - G . Part 3 c) The project length for the leadership training program development project = enter your response here days. Part 4 d) Slack time for each of the activities is: Part 5 Part 6 Part 7…Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) Time (days) A − 2 B − 5 C − 3 D B 10 E A, D 4 F C 5 G E, F 12 This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are B - D - E - G . c) The project length for the leadership training program development project = 31 days. d) Slack time for each of the activities is: Activity Slack Time A 00 B nothing C nothing D nothing E nothing F…
- Help meRoger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a num- ber of activities that must be completed before a training program of this nature could be conducted. The activities, immediate pre- decessors, and times appear in the accompanying table: 3.8 IMMEDIATE АCTIVITY PREDECESSOR(S) TIME (DAYS) A 2 5 1 10 A, D 3 F G E, F 8 a) Develop an AON network for this problem. b) What is the critical path? c) What is the total project completion time? d) What is the slack time for each individual activity? PX 6. B. B. E.Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Predecessor (S) Time (Days) A - 2 B - 5 C - 1 D B 10 E A;D 3 F C 6 G E;F 8 Which activity has the highest slack time
- Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) Time (days) A 10 B C 1 В 2 E A, D 4 F C Е, F 10 This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are c) The project length for the leadership training program development project days. %D d) Slack time for each of the activities is: Activity Slack Time A В E G1.Create the PERT -CPM on the following process. 2.Give the forward and backward pass 3.Determine the critical path. 4.Draw the its critical path. Process of Organizing a Pageant Competition TASK C G H DESCRIPTION OF ACTIVITY Create a timetable sched Plan themes and regulations Arrange catwalk setup Promote the event Market and vend tickets Secure judging panels Establish a makeup station Acquire prizes Ensure seamless pageant day Declare top scorer as the Winner Predecessor A A C D. F E, G HI Time (minutes) 12 A 8 10 9 16The City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as follows: A- Time B- Code Description (hrs) Immediate Predecessor(s) C- A Find location; determine resource requirements 25 None Requisition of lumber and sand Dig and grade Saw lumber into appropriate sizes 55 A D- C 100 A E- 30 В E Position lumber in correct locations 20 D, C F- F Nail lumber together 10 E G- Put sand in and under the equipment Put dirt around the equipment G 25 F H F H- Put grass all over the garden, landscape, paint 35 G, H Refer to the legend for the activity that corresponds to each code. Using the line drawing tool, draw a Gantt chart for activities E through I of the project. 20 40 60 80 100 120 140 160 180 200 220
- Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) Time (days) A C D 10 A, D 3 C Е, F 12 This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are days. c) The project length for the leadership training program development project = d) Slack time for each of the activities is: Activity Slack Time A C Enter your answer in each of the answer boxes. 251 DODDO DE EFGRoger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) Time (days) A − 2 B − 6 C − 2 D B 10 E A, D 3 F C 5 G E, F 8 Slack time for each of the activities is?Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) Time (days) A B C D E F G B A, D C E.F This exercise contains only parts b, c, and d b) The critical activities for the leadership training program development project are B-D-E-G c) The project length for the leadership training program development project 34 days d) Slack time for each of the activities is Activity A B Slack Time 15 7 1 10 5 6 12