Chapter 5: #12 Using MS Excel → There is a step-by-step video o Draw an activity on node (For activity D, it's predecessor is A with a Start to Start relationship and a 3 day lag) o Perform the forward and backward passes o State the critical path and project duration 12. From the following table, draw the precedence network, perform the CPM calculations, and complete the table entries, assuming interruptible activities. Activity Duration IPA 5 7 8 A B 300 с D E F G 943 10 462 AAA 2 Type Rel Lag ES EF LS LF TF FF 234 SS B C, D E, F "If the relationship type is not mentioned, it is finish to start (FS). If no lag is mentioned, it is zero. FF 2 3 2 لیا

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
100%
  1. Draw an activity on node (For activity D, it's predecessor is A with a Start to Start relationship and a 3 
    day lag) 
  2. Perform the forward and backward passes
  3.  State the critical path and project duration  
Chapter 5: #12 Using MS Excel → There is a step-by-step video
O Draw an activity on node (For activity D, it's predecessor is A with a Start to Start relationship and a 3
day lag)
o Perform the forward and backward passes
O
State the critical path and project duration
O
12. From the following table, draw the precedence network, perform the CPM
calculations, and complete the table entries, assuming interruptible activities.
Activity
A
B
с
D
E
F
G
Duration IPA Type Rel Lag ES EF LS LF TF FF
5
7
8
10
462
6
A
A
A
B
C, D
E, F
SS
SS
44
FF
2
3
2
2
"If the relationship type is not mentioned, it is finish to start (FS). If no lag is mentioned, it is zero.
Transcribed Image Text:Chapter 5: #12 Using MS Excel → There is a step-by-step video O Draw an activity on node (For activity D, it's predecessor is A with a Start to Start relationship and a 3 day lag) o Perform the forward and backward passes O State the critical path and project duration O 12. From the following table, draw the precedence network, perform the CPM calculations, and complete the table entries, assuming interruptible activities. Activity A B с D E F G Duration IPA Type Rel Lag ES EF LS LF TF FF 5 7 8 10 462 6 A A A B C, D E, F SS SS 44 FF 2 3 2 2 "If the relationship type is not mentioned, it is finish to start (FS). If no lag is mentioned, it is zero.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 6 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.