Consider a production process described by the following flowchart, on which the process time of each station is indicated. Station 1 10 min Station 2 15 min Station 3 20 min Suppose that the fixed cost for build the process is $15,000 (including the cost to build the facility, purchase of the machines, recruiting the operators, etc.). After the process is established, it is expected that it will operate at its capacity rate. The marginal profit for each unit produced is $5 (revenue minus variable cost). What is the break-even time in hours?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter12: Queueing Models
Section: Chapter Questions
Problem 59P
icon
Related questions
Question
Consider a production process described by the following flowchart, on which the
process time of each station is indicated.
Station 1
Station 2
Station 3
10 min
15 min
20 min
Suppose that the fixed cost for build the process is $15,000 (including the cost to
build the facility, purchase of the machines, recruiting the operators, etc.). After the
process is established, it is expected that it will operate at its capacity rate. The
marginal profit for each unit produced is $5 (revenue minus variable cost). What is
the break-even time in hours?
Transcribed Image Text:Consider a production process described by the following flowchart, on which the process time of each station is indicated. Station 1 Station 2 Station 3 10 min 15 min 20 min Suppose that the fixed cost for build the process is $15,000 (including the cost to build the facility, purchase of the machines, recruiting the operators, etc.). After the process is established, it is expected that it will operate at its capacity rate. The marginal profit for each unit produced is $5 (revenue minus variable cost). What is the break-even time in hours?
Expert Solution
steps

Step by step

Solved in 3 steps with 17 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS