Draw network diagram for project management and generate critical path to mark the project completion on time

Principles of Information Systems (MindTap Course List)
12th Edition
ISBN:9781285867168
Author:Ralph Stair, George Reynolds
Publisher:Ralph Stair, George Reynolds
Chapter11: Knowledge Management And Specialized Information Systems
Section: Chapter Questions
Problem 18SAT
icon
Related questions
Question

Draw network diagram for project management and generate critical path to mark the project completion on time

Activities Description
Predecessor
Duration(Weeks)
A
Event Planning
4 weeks
B
Marketing
A
3 weeks
Sponsors
В
2 weeks
D
Public Relation
1 week
Tendering Process
B
2 weeks
F
Event Production
E
8 weeks
G
Décor Design
D
10 weeks
Audio Visual Preparation
B
2 weeks
Cat & Demo
B
3 weeks
J
Final Fashions Items
F, G and I
3 weeks
K
Press & Guest Invitations
H
2 weeks
L
Setting up of Structure
J and K
3 weeks
Final Drill
L
1 week
Transcribed Image Text:Activities Description Predecessor Duration(Weeks) A Event Planning 4 weeks B Marketing A 3 weeks Sponsors В 2 weeks D Public Relation 1 week Tendering Process B 2 weeks F Event Production E 8 weeks G Décor Design D 10 weeks Audio Visual Preparation B 2 weeks Cat & Demo B 3 weeks J Final Fashions Items F, G and I 3 weeks K Press & Guest Invitations H 2 weeks L Setting up of Structure J and K 3 weeks Final Drill L 1 week
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Software cost estimation
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Information Systems (MindTap Course…
Principles of Information Systems (MindTap Course…
Computer Science
ISBN:
9781285867168
Author:
Ralph Stair, George Reynolds
Publisher:
Cengage Learning