Find the expected completion time for this project.   The expected completion time for this project is (enter your response as a whole​ number). Part 3 ​b) What variance value would be used to find probabilities of finishing by a certain​ time?   The project variance value of completion time is  ​(enter your response as a whole​ number).

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

A small software development project at Krishna​ Dhir's firm has five major activities. The times are estimated and provided in the table below.

                                                                                                                                                                                                                                                                                                                                                                                          

ACTIVITY

IMMEDIATE PREDECESSOR

a

m

 

b

 

A

1

4

 

7

 

B

2

5

 

14

 

C

A

5

11

 

17

 

D

B

3

9

 

15

 

E

C

3

3

 

3

 

Part 2

​a) Find the expected completion time for this project.

 

The expected completion time for this project is

(enter your response as a whole​ number).

Part 3

​b) What variance value would be used to find probabilities of finishing by a certain​ time?

 

The project variance value of completion time is

 ​(enter your response as a whole​ number).

 

 

A small software development project at Krishna Dhir's firm has five
major activities. The times are estimated and provided in the table
below.
ACTIVITY
A
B
C
D
E
IMMEDIATE
PREDECESSOR
A
B
C
a
1
253 3
2
5
3
3
a) Find the expected completion time for this project.
The expected completion time for this project is
response as a whole number).
m
The project variance value of completion time is
response as a whole number).
4
5
11
9
3
(enter your
b
(enter your
7
b) What variance value would be used to find probabilities of finishing
by a certain time?
14
17
15
3
Transcribed Image Text:A small software development project at Krishna Dhir's firm has five major activities. The times are estimated and provided in the table below. ACTIVITY A B C D E IMMEDIATE PREDECESSOR A B C a 1 253 3 2 5 3 3 a) Find the expected completion time for this project. The expected completion time for this project is response as a whole number). m The project variance value of completion time is response as a whole number). 4 5 11 9 3 (enter your b (enter your 7 b) What variance value would be used to find probabilities of finishing by a certain time? 14 17 15 3
Expert Solution
steps

Step by step

Solved in 5 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.