In order to meet holiday demand, Penny's Pie Shop requires a production line that is capable of producing 60 pecan pies per week, while operating only 40 hours per week. There are only 4 steps required to produce a single pecan pie with respective processing times of 4 min, 4 min, 36 min and 12 min. a. What should be the line's cycle time? minutes per pie. (Enter your response as an integer.) b. What is the smallest number of workstations Penny could hope for in designing the line considering this cycle time? stations. (Enter your response rounded up to the next whole number.) c. Suppose that Penny finds a solution that requires 3 stations. What would be the efficiency of this line? response rounded to two decimal places.) %. (Enter your
In order to meet holiday demand, Penny's Pie Shop requires a production line that is capable of producing 60 pecan pies per week, while operating only 40 hours per week. There are only 4 steps required to produce a single pecan pie with respective processing times of 4 min, 4 min, 36 min and 12 min. a. What should be the line's cycle time? minutes per pie. (Enter your response as an integer.) b. What is the smallest number of workstations Penny could hope for in designing the line considering this cycle time? stations. (Enter your response rounded up to the next whole number.) c. Suppose that Penny finds a solution that requires 3 stations. What would be the efficiency of this line? response rounded to two decimal places.) %. (Enter your
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter12: Queueing Models
Section12.5: Analytic Steady-state Queueing Models
Problem 27P
Related questions
Question
![In order to meet holiday demand, Penny's Pie Shop requires a production line that is capable of producing 60 pecan pies
per week, while operating only 40 hours per week. There are only 4 steps required to produce a single pecan pie with
respective processing times of 4 min, 4 min, 36 min and 12 min.
a. What should be the line's cycle time? minutes per pie. (Enter your response as an integer.)
b. What is the smallest number of workstations Penny could hope for in designing the line considering this cycle time?
stations. (Enter your response rounded up to the next whole number.)
c. Suppose that Penny finds a solution that requires 3 stations. What would be the efficiency of this line?
response rounded to two decimal places.)
%. (Enter your](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Fb0073743-1b87-4003-a786-266abf2414bc%2F3fc1bde4-2eed-4a2c-83b8-334b75493ee9%2Fl6jvo0s_processed.png&w=3840&q=75)
Transcribed Image Text:In order to meet holiday demand, Penny's Pie Shop requires a production line that is capable of producing 60 pecan pies
per week, while operating only 40 hours per week. There are only 4 steps required to produce a single pecan pie with
respective processing times of 4 min, 4 min, 36 min and 12 min.
a. What should be the line's cycle time? minutes per pie. (Enter your response as an integer.)
b. What is the smallest number of workstations Penny could hope for in designing the line considering this cycle time?
stations. (Enter your response rounded up to the next whole number.)
c. Suppose that Penny finds a solution that requires 3 stations. What would be the efficiency of this line?
response rounded to two decimal places.)
%. (Enter your
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 3 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Recommended textbooks for you
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,