Karamoja University has decided to build four buildings to house four departments. They have called for tenders from approved contractors for constructing the buildings. The scrutiny committee quotations for accounts felt that quotations of contractors A, B, C and D are reasonable and they decided to reject the remaining ones. The following table gives quotations in million shilling units of constructing the four buildings by the four respective contractors. Buildings III 30 28 32 34 Contractors IV A 10 24 22 20 26 15 16 12 12 10 (a) What decision the committee should make so that the amount to be spent by the University on construction is the minimum? NO6

Purchasing and Supply Chain Management
6th Edition
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
ChapterC: Cases
Section: Chapter Questions
Problem 5.3SD: Scenario 4 Sharon Gillespie, a new buyer at Visionex, Inc., was reviewing quotations for a tooling...
icon
Related questions
Question
Karamoja University has decided to build four buildings to house four departments.
They have called for tenders from approved contractors for constructing the
buildings. The scrutiny committee quotations for accounts felt that quotations of
contractors A, B, C and D are reasonable and they decided to reject the remaining
ones. The following table gives quotations in million shilling units of constructing the
four buildings by the four respective contractors.
Buildings
III
30
28
32
34
Contractors
IV
A
10
24
22
20
26
15
16
12
12
10
(a) What decision the committee should make so that the amount to be spent by
the University on construction is the minimum?
NO6
Transcribed Image Text:Karamoja University has decided to build four buildings to house four departments. They have called for tenders from approved contractors for constructing the buildings. The scrutiny committee quotations for accounts felt that quotations of contractors A, B, C and D are reasonable and they decided to reject the remaining ones. The following table gives quotations in million shilling units of constructing the four buildings by the four respective contractors. Buildings III 30 28 32 34 Contractors IV A 10 24 22 20 26 15 16 12 12 10 (a) What decision the committee should make so that the amount to be spent by the University on construction is the minimum? NO6
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning