Most Optimistic Time Likely Pessimistic Time Time Estimate Estimates Estimates Immediate Activity (weeks) (weeks) (weeks) Predecessor (s) A 6. 9 none B 5 7 A C 4 7 12 A D 4 8 10 B E 10 16 C F 3 4 5 D, E G 3 6. 8 D, E H 10 F I 8. 11 G 3 Н, I 3. 33
Q: Dr. P. Question 4 An activity in a network diagram has an optimistic time estimate of five days, a…
A: The answer is as below:
Q: a. Prepare a work breakdown structure showing tasks, durations, and predecessor tasks. b. Construct…
A: A - 2 B A 2 C A 1 D A 5 E B, C 2 F D, E 5 G F 1 Solution: a) Activity Description…
Q: Question 4. The following table shows the tasks, dependencies, and estimated times a project manager…
A: The Activity on Node diagram is as follows:
Q: Q 2/Draw the PERT network from the given Finformation in the table below: Activity 1 M 12 a 18 1 3…
A: Given Information:
Q: How many productive resources (Person) are needed on throughout each task of the project?
A: A project schedule network diagram shows the sequence of the task that is performed to complete a…
Q: Question 2. Table 2: Time Scale for Project X and Table 3: Project X's report after 10 days of…
A: An AON network diagram is shown below: Now to calculate total duration we will consider the…
Q: Using the information given and the project completiontime calculated in Problem 9(a), reduce the…
A: as information provided further to solve a part of question
Q: If the jobs displayed in Table 18.23 are processed using the earliest-due-date rule, whatwould be…
A: The earliest due date (EDD) rule gives the occupation with the earliest due date dependent on…
Q: Task Task Description Predecessors Time estimate (in minutes) te σ2 to tm tp A Slice the…
A: Drawing a network diagram can help in identifying the critical path and the critical activities…
Q: You and several friends are about to prepare a lasagna dinner. The tasks to be performed, their…
A: Note: - Since we can answer only up to three subparts we will answer the first three subparts(1, 2,…
Q: Draw the Gantt Chart with Nodes (Early Start, Early Finish, Late Start, Late Finish, Slack and…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: Practice Question EVM: A simple project consists of five tasks and is scheduled to take 13 weeks to…
A: ACWP = The actual cost of work performed is the cost actually incurred & recorded in completing…
Q: Q5. Find slack time using cpm approach? Activities Time days Immediate predecessor a A 3 6. B 2 4 4…
A: Given that: Activities a m b A 3 6 8 B 2 4 4 C 1 2 3 D 6 7 8 E 2 4 6 F 6 10 14 G 3…
Q: Consider the following work breakdown structure: Time Estimates (days) Optimistic Most Likely…
A: Critical path analysis (CPA) is a project managerial technique that represents identifying each…
Q: Act Immediate Predecessor Duration Activity Description Relationship Lag (weeks) ID (weeks) Planning…
A: The precedence relationship diagram is as follows: The possible paths are: 1) P1 - P3 - D3 - D4…
Q: ACTIVITY IMMEDIATE PREDECESSOR OPTIMISTIC TIME MOST LIKELY TIME PESSIMISTIC TIME A __________…
A: Please refer to the representation of the problem in excel : 1.What is the probability that the…
Q: Time (days) Immediate Activity a m b Predecessor(s) A 6. 9 B 4 5 1 2 D 7 В, D А, Е А, Е E 2 4 F 10…
A:
Q: Using the information given,(a) Calculate the expected time for each of the projectactivities. (b)…
A: Given data is
Q: Question 1. If the goal is to produce 180 units per hour. The tasks, task times, and immediate…
A: Since there are multiple questions, as per policy we will proceed to answer the first three…
Q: Question 13 Jassim is a 'Team Leader with a three month project to develop a new mobile phone app.…
A: In an organization, the structure, culture, framework, and design play key roles in determining the…
Q: 1- 7- 8- Jobs (i-j)2 1-3 2-3 2-4 3-5 4-6 4-8 5-6 6-7 8. Duration s (in days) 10 18 5 10 12 18 10 8 4…
A: Jobs (i-j) Duration 1-2 10 1-3 18 2-3 5 2-4 10 3-5 12 4-6 18 4-8 10 5-6 8 5-7 4…
Q: The project manager conducted a time study of the steel bending team with the times given below. The…
A: Given, The performance rating = 115% Allowance factor = 10% The standard time for the operation…
Q: 9. A work operation consisting of three (3) elements has been subjected to a time study. The…
A: Note: - Since the exact question that has to be answered is not specified we will answer the first…
Q: D Question 1 What is the earliest finish time for activity B? O 8 days O 32 days O 20 days O 12 days…
A: ES Task EF LS Time LF ES = Early Start EF = Early Finish LS = Late Start LF = Late Finish…
Q: QUESTION FOUR . 4a Poorly defined Scope of work (SOW) is a recipe for disaster and…
A: Risk is any surprising occasion that can influence your project — for better or in negative ways.…
Q: Construct a network diagram using AON notation
A: GIVEN
Q: 1. The standard time for a bank teller to process a loan form is estimated in seconds by 4 values:…
A: Estimated time in seconds 120 sec,140 sec,70sec, and 135 sec
Q: QUESTION 9 4 Aini is a network device commonly used to display project schedules. It was developed…
A: A complete handwritten solution is provided as asked by the student. Here, please refer to step 4…
Q: Activities Duration (days) Preceding activities A 5 3 7 E B F A.C 6 A.C,E 5 A,C,E 2 D. K 7 D. L…
A:
Q: You are the manager of a project to improve a billing processat your firm. Table 7.7 contains the…
A: Critical Path In project management, the longest distance between the start and the end, including…
Q: Activity / Preceding activity A/- BI- C/- D/A E/A F/A G/A,B,E H/A,D,C I/A,F Estimated time (days)…
A: Find the given details below: Activity Preceding Activity Optimistic Time(To) a(Weeks)…
Q: Which of the following is not a project management constrain Select one: O a. Time O b. Safety Oc…
A: Project management constraints are the possible limitations that can happen and that must be taken…
Q: What is the answer
A: Given data is
Q: Gabrielle Kramer, owner of Pet Paradise, is opening a new store in Columbus, Ohie. Her major concem…
A: Given Information:
Q: 15. Answer the questions that follow based on the output below (note: times are in weeks). Project…
A: “Since you have asked multiple question, we will solve the first question for you. If you want any…
Q: 1. The following table contains information on the cost to run three jobs on four available…
A: The question is related to Assignment. In given question is an unbalanced problem of minimization.…
Q: Question 6 Each descending level represents an increasingly detailed definition of the project…
A: WBS or work breakdown structure identifies all the tasks that have to be completed to build the…
Q: It costs $2 to move 1 workpiece 1 foot. What is the cost?
A: Production is the process of converting inputs into outputs. During production, there are various…
Q: Question 1 Activity Activity Description Immediate Predecessors…
A:
Q: 8. How many written days notice must you give an owner before you leave a rented apartment.* A one…
A: Since you have asked multiple questions, we will answer the first question for you. If you want a…
Q: Q. 3 What is the total makespan from Question 1? Question 1: Four floral arranging jobs are to be…
A: Given-
Q: Activity IPA Lag Duration Activity IPA Lag Duration 2 C A 2 D, E 10 A 2 E, F, G 8 3 7 7 В, С 4 K Н,…
A:
Q: Activity Immediate Predecessors Optimistic Time (a) Most Likely Time (m) Pessimistic Time (b)…
A: Given Information: Activity Immediate Predecessors Optimistic Time (a) Most Likely Time…
Q: Activity Pre-act. A B D A,B E F F,C H B H,E H,E D,I, F,C K K
A:
Q: The following information is available for a large fundraising project. Activity Activity Time…
A:
Q: Th e dean of the business school wants to start off eringthis program starting 32 weeks from now.…
A: Probability is the extent to which an event is likely to occur. It is computed by dividing the…
Using your results from Problem 6,
(a) Calculate the probability that the project will be completed
in 38 weeks.
(b) Calculate the probability that the project will be completed
in 42 weeks
Step by step
Solved in 4 steps with 2 images
- * Hame Gradebook Week 1 actice Asignmet-x O ttps//appmyeducator.com/counelactivity.t/1844/270721506109441/ Which of the following is A curent trend in consumer behavior Decreased customer need for accessing information prior to a purchase OIncreased consumer reluctance to share data with businesses they interact with O Availablity of premium options for devoted and loyal customers of a business The need to create a seamless user experience on an easy to-use company website Which of the folloving describes the form of data Kantar may present to marketers? Ut providesa qualitative and quantitative segmentation opproach that oncovers the functional, sociall and emotional drivers of consumer behvior within a given market. Ditves companies a major presence on social networking sites as this alows them to interact with their current and potensal consumers in new ways On stresses the subjective meaning of the consume's individual expertience and the idea that any behavior is subject to mutple…what are possible reasons for an observation trend?Om2. What is meant by participant observation? What are the Types of data generated by the participant observation and their advantages and disadvantages?
- Simply put, what does it mean to have an FMS choice?Develop your own psychographic instrument(set of relevant questions) that measures thelifestyles of college students.6. A consumer has chosen the model of MP3 player that he intends to purchase. On his way to the store, he has a conversation with his sister about the MP3 player he is going to buy. She expresses her opinion about MP3 players. The factor that could come between the consumer's intention to buy an MP3 player and his ultimate purchase decision is directly related to O the consumer's evaluation process for MP3 players. Ounexpected situational factors surrounding the consumer's decision. O additional consumer research on MP3 players. O another's attitude toward the chosen product.
- Can you explain what it means to have an FMS choice?List two (2) advantages and Two (2) disadvantages of the Observation Method of datacollection.Please provide 3 research problems for this question An investigation on parental involvement in their children's education and its influences on their academic performance at charlton Primary in Jamaica.