Consider the following:
Activity
A B C D E F G
с
Normal
time
4
2
3
8
6
3
4
Crash time Normal cost Crash cost Predecessor
3
1
3
4
+3~ ~
2
2
2200
2400
500
2200
600
3600
1100
What is the cost for crashing the project by 5 days?
2600
2800
500
2600
1200
4200
2000
A
B
с
D,E
Transcribed Image Text:Consider the following: Activity A B C D E F G с Normal time 4 2 3 8 6 3 4 Crash time Normal cost Crash cost Predecessor 3 1 3 4 +3~ ~ 2 2 2200 2400 500 2200 600 3600 1100 What is the cost for crashing the project by 5 days? 2600 2800 500 2600 1200 4200 2000 A B с D,E
Expert Solution
steps

Step by step

Solved in 4 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,