Premium Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2024, using 144,000 square feet of extruded vinyl purchased at $1.25 per square foot. Production required 410 direct labor hours that cost $12.00 per hour. The direct materials standard was seven square feet of vinyl per fender, at a standard cost of $1.30 per square foot. The labor standard was 0.024 direct labor hour per fender, at a standard cost of $11.00 per hour. Read the requirement. Begin with the cost variances. Select the required formulas, compute the cost variances for direct materials and direct labor, and identify whether each variance is favorable (F) or unfavorable (U). (Abbreviations used: AC = actual cost; AQ = actual quantity; FOH = fixed overhead; SC = standard cost, SQ = standard quantity.)

Principles of Accounting Volume 2
19th Edition
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax
Chapter10: Short-term Decision Making
Section: Chapter Questions
Problem 7PB: Remarkable Enterprises requires four units of part A for every unit of Al that it produces....
icon
Related questions
Question

Dont uplode any image in answer

Premium Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2024, using 144,000 square feet of
extruded vinyl purchased at $1.25 per square foot. Production required 410 direct labor hours that cost $12.00 per hour. The direct
materials standard was seven square feet of vinyl per fender, at a standard cost of $1.30 per square foot. The labor standard was 0.024
direct labor hour per fender, at a standard cost of $11.00 per hour.
Read the requirement.
Begin with the cost variances. Select the required formulas, compute the cost variances for direct materials and direct labor, and identify
whether each variance is favorable (F) or unfavorable (U). (Abbreviations used: AC = actual cost; AQ = actual quantity; FOH =
fixed overhead; SC = standard cost; SQ = standard quantity.)
Direct materials cost variance
Direct labor cost variance
11
11
Formula
Print
Requirement
Compute the cost and efficiency variances for direct materials and direct labor.
Does the pattern of variances suggest Premium Fender's managers have been
making trade-offs? Explain.
=
Done
Variance
X
Transcribed Image Text:Premium Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2024, using 144,000 square feet of extruded vinyl purchased at $1.25 per square foot. Production required 410 direct labor hours that cost $12.00 per hour. The direct materials standard was seven square feet of vinyl per fender, at a standard cost of $1.30 per square foot. The labor standard was 0.024 direct labor hour per fender, at a standard cost of $11.00 per hour. Read the requirement. Begin with the cost variances. Select the required formulas, compute the cost variances for direct materials and direct labor, and identify whether each variance is favorable (F) or unfavorable (U). (Abbreviations used: AC = actual cost; AQ = actual quantity; FOH = fixed overhead; SC = standard cost; SQ = standard quantity.) Direct materials cost variance Direct labor cost variance 11 11 Formula Print Requirement Compute the cost and efficiency variances for direct materials and direct labor. Does the pattern of variances suggest Premium Fender's managers have been making trade-offs? Explain. = Done Variance X
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College