Prob 3: Slattkey Sweets proposes to re-launch one of its mature brands, the Zubirot Bar. The brand manager has identified the tasks involved and produced the following information about them: 1 Activity H A B C D E F G Description Redesign the bar Redesign the packaging Build pilot production line Trial production run Consumer panel tests Main pilot production Design promotional material Test market redesigned product Produce report for the Board Predecessor Activity A, B C D E E F, G H Optimistic estimate of time (weeks) 5 3 10 --- 4 2 8 2 Most likely estimate of time (weeks) 8 4 13 1 1 6 4 10 2 Pessimistic estimate of time (weeks) 10 5 a. Construct the PERT/CPM network for this problem. b. What is the expected project completion time? What is the critical path? c. Determine the mean and the standard deviation for the product re-launch. d. Ascertain the probability that the project will be finished in 40 weeks. 16 2 1 9 5 15 3

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Prob 3: Slattkey Sweets proposes to re-launch one of its mature brands, the Zubirot Bar. The brand
manager has identified the tasks involved and produced the following information about them:
I
Activity
H
A
B
C
D
E
F
Description
Redesign the bar
Redesign the packaging
Build pilot production
line
Trial production run
Consumer panel tests
Main pilot production
Design promotional
material
Test market redesigned
product
Produce report for the
Board
Predecessor
Activity
A, B
C
D
E
E
F, G
H
Optimistic
estimate of
time
(weeks)
5
3
10
1
4
2
8
2
Most likely
estimate of
time
(weeks)
8
4
13
1
1
6
4
10
2
Pessimistic
estimate of
time
(weeks)
10
5
a.
Construct the PERT/CPM network for this problem.
b. What is the expected project completion time? What is the critical path?
c. Determine the mean and the standard deviation for the product re-launch.
d. Ascertain the probability that the project will be finished in 40 weeks.
16
2
1
9
5
15
3
Transcribed Image Text:Prob 3: Slattkey Sweets proposes to re-launch one of its mature brands, the Zubirot Bar. The brand manager has identified the tasks involved and produced the following information about them: I Activity H A B C D E F Description Redesign the bar Redesign the packaging Build pilot production line Trial production run Consumer panel tests Main pilot production Design promotional material Test market redesigned product Produce report for the Board Predecessor Activity A, B C D E E F, G H Optimistic estimate of time (weeks) 5 3 10 1 4 2 8 2 Most likely estimate of time (weeks) 8 4 13 1 1 6 4 10 2 Pessimistic estimate of time (weeks) 10 5 a. Construct the PERT/CPM network for this problem. b. What is the expected project completion time? What is the critical path? c. Determine the mean and the standard deviation for the product re-launch. d. Ascertain the probability that the project will be finished in 40 weeks. 16 2 1 9 5 15 3
Expert Solution
steps

Step by step

Solved in 2 steps with 6 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.