Project Total Variance Nathaniel Office 2500 18100 U Donaven Office 25850 F Zyion Office Quantity Total Variance 3200 32900 U 76850 F 4150 Actual Costs 222,400 281,350 300,000 Prepare a variance report for the purchasing department Standard Quantity Costs 2700 3500 4000 240,500 255,500 332,900

Accounting Information Systems
11th Edition
ISBN:9781337552127
Author:Ulric J. Gelinas, Richard B. Dull, Patrick Wheeler, Mary Callahan Hill
Publisher:Ulric J. Gelinas, Richard B. Dull, Patrick Wheeler, Mary Callahan Hill
Chapter15: Integrated Production Processes (ipps)
Section: Chapter Questions
Problem 4P
icon
Related questions
Topic Video
Question

Figure out what the total, price, and quantity variances are from the given information.

Please help me. 

Thankyou. 

 

Project
Total
Variance
Nathaniel Office 2500
18100
U
Donaven Office
25850 F
Zyion Office
Quantity
Total Variance
3200
32900 U
76850 F
4150
Actual
Costs
222,400
281,350
300,000
Prepare a variance report for the purchasing department
Standard
Quantity Costs
2700
3500
4000
240,500
255,500
332,900
Transcribed Image Text:Project Total Variance Nathaniel Office 2500 18100 U Donaven Office 25850 F Zyion Office Quantity Total Variance 3200 32900 U 76850 F 4150 Actual Costs 222,400 281,350 300,000 Prepare a variance report for the purchasing department Standard Quantity Costs 2700 3500 4000 240,500 255,500 332,900
Expert Solution
steps

Step by step

Solved in 3 steps with 4 images

Blurred answer
Knowledge Booster
Performance measurements
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Accounting Information Systems
Accounting Information Systems
Finance
ISBN:
9781337552127
Author:
Ulric J. Gelinas, Richard B. Dull, Patrick Wheeler, Mary Callahan Hill
Publisher:
Cengage Learning