Subject: Critical Path Method as a Project Management Technique Please answer the following questions with the need to clarify the solution method: Exercise #1: Below is a table showing the activities of a project to set up a factory. Required: Draw the project network and determine the critical path and total time to complete the project time in weeks Previous Activities Activities A B В C,D E 4 D F E, F G Is it on the late finish Late start Early end Early start Previous critical path? surplus time time in weeks time time time time Activities Activities Yes or no ? A 3 B 2 A 12 6. B C,D E 17 12 D F 17 E, F G Exercise 2: Going back to the previous exercise 1 Complete the following table from the data for the grid you drew in Exercise 1

Understanding Business
12th Edition
ISBN:9781259929434
Author:William Nickels
Publisher:William Nickels
Chapter1: Taking Risks And Making Profits Within The Dynamic Business Environment
Section: Chapter Questions
Problem 1CE
icon
Related questions
Question
i need the answer quickly
Subject: Critical Path Method as a Project Management Technique
Please answer the following questions with the need to clarify the solution method:
Exercise #1: Below is a table showing the activities of a project to set up a factory.
Required: Draw the project network and determine the critical path and total time to
complete the project
time in weeks Previous Activities
Activities
2
A
3
В
A
9
B
D
5
C, D
E
4
D
2
Е, F
G
Is it on the
late finish
Late start
Early
end
Early start
Previous
critical path?
surplus time
time in weeks
time
time
time
time
Activities
Activities
Yes or no ?
5
A
3
3
B
2
12
D
C,D
E
--
17
12
D
F
17
E, F
G
Exercise 2: Going back to the previous exercise 1 Complete the following table from
the data for the grid you drew in Exercise 1
Transcribed Image Text:Subject: Critical Path Method as a Project Management Technique Please answer the following questions with the need to clarify the solution method: Exercise #1: Below is a table showing the activities of a project to set up a factory. Required: Draw the project network and determine the critical path and total time to complete the project time in weeks Previous Activities Activities 2 A 3 В A 9 B D 5 C, D E 4 D 2 Е, F G Is it on the late finish Late start Early end Early start Previous critical path? surplus time time in weeks time time time time Activities Activities Yes or no ? 5 A 3 3 B 2 12 D C,D E -- 17 12 D F 17 E, F G Exercise 2: Going back to the previous exercise 1 Complete the following table from the data for the grid you drew in Exercise 1
Expert Solution
steps

Step by step

Solved in 4 steps with 3 images

Blurred answer
Knowledge Booster
Business reports
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Understanding Business
Understanding Business
Management
ISBN:
9781259929434
Author:
William Nickels
Publisher:
McGraw-Hill Education
Management (14th Edition)
Management (14th Edition)
Management
ISBN:
9780134527604
Author:
Stephen P. Robbins, Mary A. Coulter
Publisher:
PEARSON
Spreadsheet Modeling & Decision Analysis: A Pract…
Spreadsheet Modeling & Decision Analysis: A Pract…
Management
ISBN:
9781305947412
Author:
Cliff Ragsdale
Publisher:
Cengage Learning
Management Information Systems: Managing The Digi…
Management Information Systems: Managing The Digi…
Management
ISBN:
9780135191798
Author:
Kenneth C. Laudon, Jane P. Laudon
Publisher:
PEARSON
Business Essentials (12th Edition) (What's New in…
Business Essentials (12th Edition) (What's New in…
Management
ISBN:
9780134728391
Author:
Ronald J. Ebert, Ricky W. Griffin
Publisher:
PEARSON
Fundamentals of Management (10th Edition)
Fundamentals of Management (10th Edition)
Management
ISBN:
9780134237473
Author:
Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:
PEARSON