The Old Hickory Furniture Company manufactures chairs on the basis of the BOM shown below. At the present time, the inventories of parts and lead times are as follows: Chairs Leg assembly Back assembly Seat Rails Legs Top Spindles Chair Leg assembly Rails Back assembly Legs Top On Hand 100 50 25 40 100 150 30 80 Seat Spindles Weeks of Lead Time 1 2 1 3 1 1 2 2 The firm would like to produce 600 chairs in week 5 and 300 chairs in week 6. a. Develop a materials plan for all the parts using L4L. b. What actions should be taken now? c. Assume it takes one hour to assemble backs, one hour to assemble legs, and two hours to finish completed chairs. Total assembly time for all three types of assembly is limited to 1000 hours per week. Will this capacity constraint cause a bottleneck in assembly? If it does, what can be done?

ENGR.ECONOMIC ANALYSIS
14th Edition
ISBN:9780190931919
Author:NEWNAN
Publisher:NEWNAN
Chapter1: Making Economics Decisions
Section: Chapter Questions
Problem 1QTC
icon
Related questions
Question
4. The Old Hickory Furniture Company manufactures chairs on the basis of the BOM shown below.
At the present time, the inventories of parts and lead times are as follows:
Chairs
Leg assembly
Back assembly
Seat
Rails
Legs
Top
Spindles
Chair
Leg
assembly
Rails
Back
assembly
Legs Top
(4)
On Hand
100
50
25
40
100
150
30
80
Seat
Spindles
Weeks of Lead Time
1
2
1
3
1
1
2
2
The firm would like to produce 600 chairs in week 5 and 300 chairs in week 6.
a. Develop a materials plan for all the parts using L4L.
b. What actions should be taken now?
c. Assume it takes one hour to assemble backs, one hour to assemble legs, and two hours to finish
completed chairs. Total assembly time for all three types of assembly is limited to 1000 hours
per week. Will this capacity constraint cause a bottleneck in assembly? If it does, what can be
done?
d. What is the effect of changing the master schedule to 300 chairs in week 5 and 400 chairs in
week 6?
Transcribed Image Text:4. The Old Hickory Furniture Company manufactures chairs on the basis of the BOM shown below. At the present time, the inventories of parts and lead times are as follows: Chairs Leg assembly Back assembly Seat Rails Legs Top Spindles Chair Leg assembly Rails Back assembly Legs Top (4) On Hand 100 50 25 40 100 150 30 80 Seat Spindles Weeks of Lead Time 1 2 1 3 1 1 2 2 The firm would like to produce 600 chairs in week 5 and 300 chairs in week 6. a. Develop a materials plan for all the parts using L4L. b. What actions should be taken now? c. Assume it takes one hour to assemble backs, one hour to assemble legs, and two hours to finish completed chairs. Total assembly time for all three types of assembly is limited to 1000 hours per week. Will this capacity constraint cause a bottleneck in assembly? If it does, what can be done? d. What is the effect of changing the master schedule to 300 chairs in week 5 and 400 chairs in week 6?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps

Blurred answer
Knowledge Booster
Profit Maximization
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
ENGR.ECONOMIC ANALYSIS
ENGR.ECONOMIC ANALYSIS
Economics
ISBN:
9780190931919
Author:
NEWNAN
Publisher:
Oxford University Press
Principles of Economics (12th Edition)
Principles of Economics (12th Edition)
Economics
ISBN:
9780134078779
Author:
Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:
PEARSON
Engineering Economy (17th Edition)
Engineering Economy (17th Edition)
Economics
ISBN:
9780134870069
Author:
William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:
PEARSON
Principles of Economics (MindTap Course List)
Principles of Economics (MindTap Course List)
Economics
ISBN:
9781305585126
Author:
N. Gregory Mankiw
Publisher:
Cengage Learning
Managerial Economics: A Problem Solving Approach
Managerial Economics: A Problem Solving Approach
Economics
ISBN:
9781337106665
Author:
Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:
Cengage Learning
Managerial Economics & Business Strategy (Mcgraw-…
Managerial Economics & Business Strategy (Mcgraw-…
Economics
ISBN:
9781259290619
Author:
Michael Baye, Jeff Prince
Publisher:
McGraw-Hill Education