You are given the following data for an activity: ES = 10 EF = 15 LS = 16 Which of the following can you determine from this data? A. The activity's float and duration B. Only the activity float C. Only the activity duration D. Neither the activity's float nor its duration
Q: Observe the given activities of a Project. You are required to have sort and schedule the following…
A: Gantt chart - A Gantt chart, or harmonogram, is a type of bar chart that illustrates a project…
Q: Which of the following statements regarding Gantt charts istrue?a) Gantt charts give a timeline and…
A: A Gantt chart is basically a kind of bar chart that displays the project schedule. It conveys the…
Q: Consider two projects that have the same activities and the same dependencies. In thefirst project,…
A: The second project will be completed first.
Q: In the project considered below, activity crashing can take place over a wide range of reduction…
A: given,
Q: What is the current progress of the project? The budgeted cost for work scheduled is 700k. Is it on…
A: The two project performance measurements, that can be used are Sceduled performance index and Cost…
Q: Project Managers must demonstrate (4) activities: Project planning: ◦Project scheduling:◦Project…
A: Project management is the management in which special skills, knowledge, and information are…
Q: true/false 25)Activity codes are used for filtering in reports. 26) Start/Finish updating is best…
A: Since you have asked multiple questions, we will solve the first question for you. If you want any…
Q: Discuss possible causes for change in projects and their budgets and/or schedules. Any reference…
A: A project would include several factors from different sectors and each factor contribute to the…
Q: The use of probability curves to describe a project estimate helps to deal with: Your answer: The…
A: Estimation is an important skill required by many professionals. Estimates as probability…
Q: a. Using the normal times for each activity, what is the earliest date you can complete the project?…
A: A project schedule network diagram shows the sequence of the tasks that are performed to complete a…
Q: A project manager is in charge of a project, and while they agree that a 60-hour work week is…
A: According to the question, we need to select three project management tactics, these tactics are…
Q: How long it will take for each activity on the network chart is all but one of the following. O…
A: Answer: Estimated duration
Q: Which of the following statements is correct with respect to slack time?a. The slack time of an…
A: Slack time in any production unit is the time available between various steps of a project. In other…
Q: Indicate and briefly explain the different control levers that may be used to a project
A: For a long time, the three levers theory was regarded as one of the most significant project…
Q: Consider a project to produce custom door moldingsfor GMC Acadia cross-over vehicles, described…
A: Given data is
Q: Select the correct answer. Paul is the CEO of a mid-sized IT firm. Three weeks ago, he started a new…
A: As significant as investigating a project lifecycle, dealing with a project adequately implies…
Q: Evaluate the below statement according to the estimation of activity duration tools, write the…
A: 1) Makes use of group intelligence to determine the activity duration, scaling up or down the…
Q: IT project management A project requires the conducting or performing of the following three tasks…
A: Activity sequencing techniques are some methods that are used to understand different relationship…
Q: You are in charge of a project at the local community center. The center needs to remodel one of the…
A: Project crashing is a process of reducing the total project completion time based on the day-based…
Q: Which of the following rules for the construction of a PERT diagram is INCORRECT? a. An event is not…
A: PERT diagram is the project management tool that is used to track the tasks and their timelines. It…
Q: In Unit VIII, you are required to submit a management action plan (MAP). Instructions for this…
A: Changes in the industry of health care are affecting the organization of health care. With changes…
Q: The main tool for managing the project scope, as described in PMBOK, is the O project charter O…
A:
Q: A B T= 4 T= 3 F T= 3 T= 3 D E G T= 1 T= 2 T= 2 The network diagram of a project along with the…
A: The project network is the diagram that shows the order of completion of project network activities…
Q: Questions 1 through 5 are based on the following information. ABC Company is launching a new product…
A: Using Formula; Expected time = Optimistic Time+4*Most Likely Time+Pessimistic Time6
Q: 1. Organize the information above in an activity precedence table. 2. Draw an Activity-On-Arrow…
A: Below is the solution:-
Q: The client of a project has requested the project team to crash 8 hours of time. The table below…
A: The network diagram for the above network is as below. I have used principles of AON network…
Q: You are given the following parameters for a project. There is an opportunity to upload your work in…
A: CPM stands for Critical Path Method, which was invented by DuPont and first used in the chemical…
Q: The management and oversight of scope modifications within the project has an impact on the…
A: In project management, a scope tells us how a project will function and perform based on the goals…
Q: 1. Calculate the total time for all primary activities. fill in the blank hours
A: Since you have asked multiple questions, we will solve the first question for you. If you want any…
Q: Issues in project management include a. level of effort. b. period of performance. c.…
A: Budgeting issues Most managers think about monetary issues as probably the greatest obstacle in…
Q: You are in charge of a project at the local community center. The center needs to remodel one of the…
A: For the first part, let us calculate the early finish and early start time for each of the…
Q: (a) Draw a project network. (Submit a file with a maximum size of 1 MB.) Choose File no file…
A: D(duration)=given in the question as normal time ES (Early start)= The first activity from where the…
Q: Suppose that you are assigned to a construction project which is planned to be build as early as…
A: A Gantt chart:It is a project management mechanism helping in the outlining & scheduling of the…
Q: List and briefly describe the various levers that can be used to exert control over a project.
A: There are seven levers which are described below that can be used to exertcontrol over a project.
Q: Consider a project to produce custom door moldings for GMC Acadia cross-over vehicles, described in…
A: Slack is the time by which a task can be delayed without causing a delay in the subsequent task. It…
Q: For a given activity, the: most optimistic time to complete the project is 8, the most pessimistic…
A: CPM stands for Critical Path Method, which was invented by DuPont and first used in the chemical…
Q: The following criteria is NOT being considered for crashing an activity or the entire project. a)…
A: Project crashing is reducing the time of a few tasks or activities in a project, to shorten the…
Q: A bar chart shows the number and type of resources you need throughout your project is called a…
A: The Resource Histogram is a bar chart that shows your staffing needs over time. If you need more…
Q: What is the latest that activity B can start if A lasts 35 days, B lasts 5, days C lasts 6 days, and…
A: Given data is
Q: A _____ is a method of incorporating change into project planning and execution processes.…
A: A Small Introduction about Project Planning A project plan comprises angles like destinations,…
Q: For projects that are complicated and more factors can influence the duration, reasonably costly.…
A: As per the given two statement-
Q: Which of the following statements regarding Gantt charts is true? a) Gantt charts give a timeline…
A: Gantt chart is defined as the tool of project management which assist in the scheduling as well as…
Q: Which of the following is a source of qualitative information available to project managers? Project…
A: Qualitative information refers to the information which describes the quality and characteristics of…
Q: draw the unscaled activity bar type based on early start and late start
A: Given data is
You are given the following data for an activity: ES = 10 EF = 15 LS = 16 Which of the following can you determine from this data?
A. The activity's float and duration
B. Only the activity float
C. Only the activity duration
D. Neither the activity's float nor its duration
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 2 images
- You may need to use the appropriate technology to answer this question. Management Decision Systems (MDS) is a consulting company that specializes in the development of decision support systems. MDS has a four-person team working on a current project with a small company to set up a system that scrapes data from a collection of websites and then automatically generates a report for management on a daily basis. Time (Weeks) Activity A B с Description Report generation 5 Web scraping Testing img20230305_11125728.pdf Immediate Predecessor A, B Optimistic 1 4 1 (a) Construct the project network. (Submit a file with a maximum size of 1 MB.) Choose File No file chosen Most Probable 8 9 1 Pessimistic 12 (d) Should you use the estimate in (b) or (c)? O The probability estimate from (b) based on the critical path is more accurate. The probability estimate from (c) based on both paths is more accurate. O The probability estimates from (b) and (c) are equal. 11 1 (b) Based solely on the critical…1 The following graph shows data about the height of a bamboo plant after a certain number of days. (At home writers, you must either print this graph or re-draw accurately on a piece of graph paper, time will be extended to allow for this) a) What does each point on the scatterplot represent? 180- -170 -160 -150 -140 130 120 -110 100 b) How tall might the plant be on day 7? Is this an example of interpolation, extrapolation, or neither? Justify. -90 -80 70 -60 -50 -40 -30 -20 -10 c) How tall might the plant be on day 13? Is this an example of interpolation, extrapolation, or neither? Justify. Time (days) Height of Plant (cm)Management Decision Systems (MDS) is a consulting company that specializes in the development of decision support systems. MDS has a four-person team working on a current project with a small company to set up a system that scrapes data from a collection of websites and then automatically generates a report for management on a daily basis. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Report generation 1 8 12 B Web scraping 4 9 11 C Testing A, B 1 1 1 (b) Based solely on the critical path, estimate the probability that the project will be complete within 11 weeks. (Round your answer to four decimal places.) (c) Using all paths through the project network, estimate the probability that the project will be complete within 11 weeks. (Round your answer to four decimal places.)
- Management Decision Systems (MDS) is a consulting company that specializes in the development of decision support systems. MDS has a four-person team working on a current project with a small company to set up a system that scrapes data from a collection of websites and then automatically generates a report for management on a daily basis. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Report generation 2 9 13 B Web scraping 6 10 12 C Testing A, B 1 1 1 (a) Construct the project network. (Submit a file with a maximum size of 1 MB.) This answer has not been graded yet. (b) Based solely on the critical path, estimate the probability that the project will be complete within 12 weeks. (Round your answer to four decimal places.) (c) Using all paths through the project network, estimate the probability that the project will be complete within 12 weeks. (Round your answer to four decimal places.) (d)…2-41 The time to complete a construction project is normally distributed with a mean of 60 weeks and a standard deviation of 4 weeks. a. What is the probability the project will be finished in 62 weeks or less? b. What is the probability the project will be finished in 66 weeks or less? c. What is the probability the project will take longer than 65 weeks?You may need to use the appropriate technology to answer this question. Management Decision Systems (MDS) is a consulting company that specializes in the development of decision support systems. MDS has a four-person team working on a current project with a small company to set up a system that scrapes data from a collection of websites and then automatically generates a report for management on a daily basis. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Report generation 2 9 13 B Web scraping 6 10 12 C Testing A, B 1 1 1 (a) Construct the project network. (Submit a file with a maximum size of 1 MB.) (b) Based solely on the critical path, estimate the probability that the project will be complete within 12 weeks. (Round your answer to four decimal places.) (c) Using all paths through the project network, estimate the probability that the project will be complete within 12 weeks. (Round your answer to…
- You may need to use the appropriate technology to answer this question. Management Decision Systems (MDS) is a consulting company that specializes in the development of decision support systems. MDS has a four-person team working on a current project with a small company to set up a system that scrapes data from a collection of websites and then automatically generates a report for management on a daily basis. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Report generation 2 9 13 B Web scraping 6 10 12 C Testing A, B 1 1 1 (a) Construct the project network. (Submit a file with a maximum size of 1 MB.) This answer has not been graded yet. (b) Based solely on the critical path, estimate the probability that the project will be complete within 12 weeks. (Round your answer to four decimal places.) (c) Using all paths through the project network, estimate the probability that the project will be…You may need to use the appropriate technology to answer this question. Management Decision Systems (MDS) is a consulting company that specializes in the development of decision support systems. MDS has a four-person team working on a current project with a small company to set up a system that scrapes data from a collection of websites and then automatically generates a report for management on a daily basis. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Report generation 2 9 13 B Web scraping 6 10 12 C Testing A, B 1 1 1 (a) Construct the project network. (Submit a file with a maximum size of 1 MB.) please help with this one This answer has not been graded yet. (b) Based solely on the critical path, estimate the probability that the project will be complete within 12 weeks. (Round your answer to four decimal places.)90.8240 i got this and this is wrong answer. (c) Using all paths through the…Please help with correct answers! Management Decision Systems (MDS) is a consulting company that specializes in the development of decision support systems. MDS has a four-person team working on a current project with a small company to set up a system that scrapes data from a collection of websites and then automatically generates a report for management on a daily basis. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Report generation 2 9 13 B Web scraping 5 10 12 C Testing A, B 1 1 1 a) Based solely on the critical path, estimate the probability that the project will be complete within 12 weeks. (Round your answer to four decimal places.) b) Using all paths through the project network, estimate the probability that the project will be complete within 12 weeks. (Round your answer to four decimal places.)
- Please do not give solution in image formate thanku. 11-24 Using PERT, Ed Rose was able to determine that the expected project completion time for the construction of a pleasure yacht is 21 months and the project variance is 4. What is the probability that the project will be completed in 17 months or less? What is the probability that the project will be completed in 20 months or less? What is the probability that the project will be completed in 23 months or less? What is the probability that the project will be completed in 25 months or less?Topic: ProbabilityGoal: In your business planning, you will employ mathematics probability to increase your chances of success.You play the role of a tiny business owner who wants to expand into a much larger enterprise. You must write a written report and deliver it to the group on the most likely outcome(s) of the business you wish to start.The target audience is a group of small company owners who could be interested in partnering with you. Product: A written report on the business's likely results that will be given to the group. Success Criteria: The written report that will be provided must be... - Represents genuine business problems or patterns. - Persuasive, based on probability mathematics.Company XYZ is specialized in producing and selling smart watches. The company currently has two products and is planning to improve it profits in the coming years. The company is thinking of introducing a sales commission to encourage its sales people to make more sales and improve company's profitability. When designing the sales commission the company should base the sales commission on: a. The color of the product O b. The contribution margin The number of employees O d. None of the given answers e. The selling price