You have solved a 3-variable maximisation Linear Program with the objective function of z = 4x1 + 3x2 + 7x3. The Linear Program has two "s" constraints, and its optimal solution is as follows: (x₁, x₂, x3, S₁, S₂) = (7,0,0,2,0), z* = 28. Consider the following situations: • The objective function changes to maximise z = 4x₁ + 7x2 + 7x3. • The objective function changes to maximise z = 3x₁ + 3x2 + 7x3. For each situation above, analyse separately and specifically what must be checked if you were to determine whether the current basis remains optimal after the change is made. Justify your answers.
Q: Choose the best answer. The Production Planning Hierarchy: Box "C" A B CD Strategic Planning…
A: STRATEGIC PLANNING: Strategic planning in production can be defined as an overall planning which is…
Q: James Beerd bakes cheesecakes and Black Forest cakes. During any month, he can bake at most 65…
A:
Q: n use any 5 (FIVE) quality dimensions to differentiate a product
A: To be of high quality means to be free from defects, shortages, and major variations, as well as to…
Q: 2458) A manufacturing company produces two lines of designer gates, called model A and model B.…
A: Given data is Profit by model A = $90 Profit by model B = $80 Required by model A Required by…
Q: 1. Southern Sporting Goods Company makes basketballs and footballs. Each product is produced from…
A: Objective Functions and Constraints: Based on the given details, the objective…
Q: By using Vogel's approximation method, .find the basic starting solution
A: The transportation model is used to calculate the minimum cost of the route by selecting different…
Q: A company is designing a product layout for a new product. It plans to use this production line…
A: Cycle Time = Time available per day / Units required per day
Q: When will the project be completed?
A: Project network diagram is the diagram that visually represent the project activities and their…
Q: 7.50 During recessionary periods, bonds that were issued many years ago have a higher coupon rate…
A:
Q: A firm is attempting to minimize its shipping costs. The firm has 3 factories and must supply the…
A: On tabulating the given data in excel, we will get a similar table as shown in the original answer.…
Q: How is peculative production related to a firm’s cash-flow problems?
A: Speculative production refers to the break time between the production of goods and the sale of…
Q: absenteesim relating to minor and major illness
A: Sickness absenteeism (SA) is a phenomenon that entails a work disability arising from illness or…
Q: What is JIT?
A: Just in Time is an inventory management system whose objective is to produce or to procure products…
Q: 1. Formulate a linear programming model for Angela and Zooey that will help them estimate the number…
A: Linear programming is a mathematical technique that is also used in operations management…
Q: Sam just started work with Caprese Co. Sam will work at their offices from Monday to Friday, 9-5pm.…
A: Employee engagement is a human resources (HR) term that emphasizes a worker's excitement and…
Q: A manufacturer of plastics is planning to blend a new product from for ical compounds. These…
A: Lets A1 , A2 , A3 , A4 be the amount of each compound in each the product . min B =…
Q: What qualities does a project need to be able to use critical path scheduling?
A: Critical path scheduling is an invaluable tool that project managers have at their disposal. Without…
Q: Q5: Reduce the following project activity Normal Time Cost 1-2 3 300 2-3 6 480 7 2100 8 400 4 320 5…
A: The question is related to Crashing of Project. Project Crashing deal with those situations which…
Q: Find the optimal solution for the following problem. (Round your answers to 3 decimal places.)…
A: Max Z = 18x + 23y +10zSubject to14x + 16y +23z ≤569x + 0y +7z≤112x, y, z ≥0
Q: ation and enhances competitive advantage for the organisation. Using practical examples and…
A: Maintaining a private venture frequently implies the buck starts and stops with you. Yet, to draw in…
Q: Betty Malloy, owner of the Eagle Tavern in Pittsburgh, is preparing for Super Bowl Sunday, and she…
A: Given data is Cost of Yodel = $1.50/gallon Cost of Shotz = $0.90/gallon Cost of Rainwater =…
Q: The number of salespeople assigned to work during a shift is apportioned based on the average number…
A:
Q: hers in Boston was $13,579 d the entry-level salary have
A: Given: Entry-level salary for teachers in 1981 is $13579 It rises to $45498 in 2017 (a) Based on CPI…
Q: The officers should rent buses and [ The minimal transportation costs are S vans to minimize the…
A: Linear programming is a mathematical technique that is also used in operations management…
Q: Consider the transportation table below. (a) Use the Northwest-Corner Method, the Least-Cost Method…
A: Find the given details below: Given details: Factory Warehouse A B C D Supply 1 4 7 7 1…
Q: MNP Ltd sold 2,75,000 units of its product at 37.50 per unit. Variable costs are 17.50 per unit…
A: Breakeven Point is that level of sales at which there is no profit no loss. It is calculated with…
Q: A quality control technique for tracing back from observed problems to likely causes is:…
A: The control chart is a graph that is used to study the changes within the process over the time…
Q: Outlook Gateways has a demand of 75 Lakhs per year. Setup cost and holding cost are 29 and 35 per…
A:
Q: BERNARDS COMPANY LTD is a PRODUCER of fruit juices. The company has an annual demand of 150,000…
A: Annual Demand = D = 150,000 barrels Cost per barrel = C = $30 Ordering Cost = S = $400 Annual…
Q: A firm uses simple exponential smoothing with trend adjustment to forecast demand, "a = 0.6" and…
A: Given, TAF for first month TAF1 = 434 units Actual demand for first period A1= 488 units Trend T1 =…
Q: What are the Importance of quality to the national interest of any country?
A: The term quality can be understood as fulfillment of certain prescribed standards. A quality product…
Q: 4. What is the difference between competitive advantage and sustainable competitive advantage? 5.…
A: Since you have asked multiple questions, we will solve anyone for you, hence solving the first…
Q: Kanban container size = Number of kanbans needed=
A:
Q: GENERATE GENERATE THE DECISION VARIABLE SOLUTION AND A SENSITIVITY REPORT 2. During the winter…
A: Let, R = Number of residential jobs C = Number of commercial jobs Objective function: Maximize Z =…
Q: List and explain the types of jobs today that would require time and motion studies to be a factor?…
A: Time and motion studies are an important part of improving workplace efficiency and understanding…
Q: Dags pe t the local farmers' market. shelled pecans for $7, and of an unshelled pecan. It requ…
A: Based on given information have to determine the decision variables: X1=Pies X2=Batches of one dozen…
Q: Consider the following problem: A company supplies goods to three customers, who each require 30…
A: Find the given details below: Transportation Schedule From/To Customer 1 Customer 2 Customer 3…
Q: 31) Use the values in the table to calculate activity durations and variances for the project. Which…
A: Network diagram: Calculation of expected time and variance with given Optimistic, pessimistic and…
Q: ost-Perry Industries (YPI) manufactures a mix of affordable guitars (A, B, C) that are fabricated…
A: Bottleneck station is the one which has least output capacity. time available = 40 hours time…
Q: Instructions ASSIGNMENT PROJECT SCENARIO: You are married and you are the father or mother of a…
A: As given in the instructions, the camping trip needs to be considered a project. The project team…
Q: a. How many decision variables will the linear programming model include? Number of decision…
A: Linear programming is a mathematical technique that is also used in operations management…
Q: Examples of Control Systems Models or Representations with explanation.
A: The control systems can be represented with a set of mathematical equations known as mathematical…
Q: Q1: An electrical engineer wants to finish his new device production project within 47 days to meet…
A: Project Crashing deal with those situations which will speak of the effect of increase or decrease…
Q: how does family related issues lead to absenteesim
A: Employee absenteeism can be stated as the constant and repetitive pattern of absence from jobs or…
Q: If the coefficient for Activity 2 in the objective function changes to $400, then the objective…
A: The allowable increase of activity 2 is 500. This means that the objective coefficient of activity 2…
Q: To get things started, why is it essential for young professionals like students, interns, and…
A: Operation management is an important part of management where the manager is responsible for…
Q: The smallest defect in a computer chip will render the entire chip worthless. Therefore, tight…
A: Given data Sample size (n) = 1000 Defective size or percentage of defects = 1.5% Z-score = 3
Q: Electronics, Inc., in Nashv ces sn runs of custom ain ve scanners for the defense industry. You have…
A: In a manufacturing process, a kanban system is a form of inventory control that uses cards or tags…
Q: Use the following Profit decision tree and calculate the EVPI. **Enter the number only. Do not enter…
A: Here, the prior probabilities and posterior probabilities are given. Prior Probability: Posterior…
Q: of a descriptive mod
A: descriptive model
operation research
Step by step
Solved in 3 steps
- FIND THE OPTIMUM SOLUTION TO X= Y= MAX Z=Facility Location. A paper products manufacturer has enough capital to build and manage some additional manufacturing plants in the United States in order to meet increased demand in three cities: New York City, NY; Los Angeles, CA; and Topeka, KS. The company is considering building in Denver, CO; Seattle, WA; and St. Louis, MO. Max Operating Capacity 400 tons/day 700 tons/day Denver Seattle $10/ton $17/tor $5/ton $11/ton.... $18/ton.... $28/ton Los Angeles Topeka New York City Figure 1: Graphical representation of the given data = • The cost fi of building plants in these cities is fi $10,000,000 in Seattle. Unmet Demand 300 tons/day 100 tons/day 500 tons/day • Due to geographic constraints, plants in Denver and Seattle would have a maximum operating capacity kį of 400 tons/day and 700 tons/day respectively. $5,000,000 in Denver and f2 = • The cost cij per ton of transporting paper from city i to city j is outlined in Figure 1. • The unmet demand d, for Los Angeles, Topeka, and New…Show that any 2 *2 matrix A that does not have aninverse will have det A= 0.
- Dickie Hustler has $2 and is going to toss an unfair coin(probability .4 of heads) three times. Before each toss, hecan bet any amount of money (up to what he now has). Ifheads comes up, Dickie wins the number of dollars he bets;if tails comes up, he loses the number of dollars he bets.Use dynamic programming to determine a strategy thatmaximizes Dickie’s probability of having at least $5 afterthe third coin toss.. Consider the following linear programming problem: Maximize 12X + 10Y Subject to: 4X + 3Y = 480 2X + 3Y 360 all variables 20 Which of the following points (X,Y) is not feasible? a (70,70) b. (20,90) c. (100,10) d. (0,100) كلا أجرب الأرقام بالـؤالSolve the following Linear Programming model using the graphical method (USING EXCEL){Write the steps of construction} Q1)MaximizeH = x + 3y Objective functionsubject tox + y ≤ 502x + y ≤ 60 x ≥ 0, y ≥ 0
- Multiple Optimal Solution: Example (9): Find the optimal solution for the : Multiple Optimal following model by the graphical method Max Z = X,+X, X, +X, 23 .(1) X, +X, 56 S. to : X,21 ..(2) .(3) X, s2 (4) X, 20 X, 20Solve the linear programming problem by the method of corners. Maximize P= x + 6y subject to x + y s4 2x + y s6 x 2 0, y 20 The maximum is P = at (x, y) = Need Help? Read ItA college student works in both the school cafeteria and library. She works no more than 12 hours per week at the cafeteria, and no more than 16 hours per week at the library. She must work at least 20 hours each week. Write a system of inequalities that describes all the given conditions. Write a system of inequalities letting x= number of hours worked at the cafeteria per week and y = number of hours worked at the library per week. x+yz x≤ ys
- Combined-cycle power plants use two combustion turbines to produce electricity. Heat from the first turbine’s exhaust is captured to heat waterand produce steam sent to a second steam turbine that generates additional electricity. A 968-megawatt combined-cycle gas fired plant can be purchased for $450 million, has no salvage value, and produces a net cash flow(revenues less expenses) of $50 million per year over its expected 30-year life. Solve, a. If the hurdle rate (MARR) is 12% per year, how profitable an investment is this power plant? b. What is the simple payback period for the plant? Is this investment acceptable?Long-Life Insurance has developed a linear model that it uses to determine the amount of term life Insurance a family of four should have, based on the current age of the head of the household. The equation is: y=150 -0.10x where y= Insurance needed ($000) x = Current age of head of household b. Use the equation to determine the amount of term life Insurance to recommend for a family of four of the head of the household is 40 years old. (Round your answer to 2 decimal places.) Amount of term life insurance thousandsThe High-Price Oil Company owns a pipeline network that is used to convey oil from its source to several storage locations. A portion of the network is as follows: Due to the varying pipe sizes, the flow capacities vary. By selectively opening and closing sections of the pipeline network, the firm can supply any of the storage locations. a. If the firm wants to fully utilize the system capacity to supply storage location 7, how long will it take to satisfy a location 7 demand of 100,000 gallons? What is the maximal flow for this pipeline system? b. If a break occurs on line 2–3 and that line is closed down, what is the maximal flow for the system? How long will it take to transmit 100,000 gallons to location 7?