Several years after reengineering its production process, Dettling Corporation hired a new controller, Alana Metzgar. She developed an ABC system very similar to the one used by Dettling’s chief rival. Part of the reason Metzgar developed the ABC system was because Dettling’s profits had been declining, even though the company had shifted its product mix toward the product that had appeared most profitable under the old system. Before adopting the new ABC system, the company had used a plantwide overhead rate based on direct labor hours that was developed years ago.
For the upcoming year, Dettling’s budgeted ABC manufacturing overhead allocation rates are as follows:
Activity | Allocation Base | Activity Cost Allocation Rate |
Materials handling | Number of parts | $ 4.50 per part |
Machine setup | Number of setups | $325.00 per setup |
Insertion of parts | Number of parts | $ 31.00 per part |
Finishing | Finishing direct labor hours | $ 51.00 per hour |
The number of parts is now a feasible allocation base because Dettling recently installed a plantwide computer system. Dettling produces two wheel models: Standard and Deluxe. Budgeted data for the upcoming year are as follows:
Standard | Deluxe | |
Parts per wheel | 4.0 | 6.0 |
Setups per 1,000 wheels | 20.0 | 20.0 |
Finishing direct labor hours per wheel | 1.0 | 3.0 |
Total direct labor hours per wheel | 2.7 | 3.8 |
The company’s managers expect to produce 1,000 units of each model during the year.
Requirements
- 1. Compute the total budgeted
manufacturing overhead cost for the upcoming year. - 2. Compute the manufacturing overhead cost per wheel of each model using ABC.
- 3. Compute the company’s traditional plantwide overhead rate. Use this rate to determine the manufacturing overhead cost per wheel under the traditional system.
Trending nowThis is a popular solution!
Learn your wayIncludes step-by-step video
Chapter 4 Solutions
Managerial Accounting (5th Edition)
Additional Business Textbook Solutions
Principles of Accounting Volume 2
Financial Accounting (12th Edition) (What's New in Accounting)
Financial Accounting, Student Value Edition (4th Edition)
Intermediate Accounting
Horngren's Financial & Managerial Accounting, The Managerial Chapters (6th Edition)
Financial Accounting (11th Edition)
- The Wake Sally worked as a project manager for a high-tech electronics firm in the late 1980s. The company was using "bubble ink" technology to develop affordable color printers. Sally was in charge of a team tasked with cutting the prohibitive cost of printers in half. If successful, significant bonuses would be earned and several team members would be given key positions when the product went into production. The team had overcome several difficult technical challenges and was well on its way to accomplishing their objective when the project was canceled. Top management discovered at a trade show that several competitors were about to introduce ink jet printers at a cost one-third the price of printers Sally's team was developing. What could Sally say to her team? They had worked so hard, expected so much out of this project. She knew they would be devastated. Sally knew she had to do something to help them deal with this bitter disappointment. So she decided to hold a traditional…arrow_forwardRUE BENNETT Company develops software for small businesses and household computers. The majority of the company's computer programmers are working on developing software that will perform relatively specialized functions in a user-friendly manner. Before the working model is released to production for the preparation of masters and additional testing, it undergoes extensive testing. As a result of this meticulous planning, various computer software packages have been developed that have proven to be very successful in the industry. RUE BENNETT Company incurred the following costs during 2020: Cost to reproduce and prepare software for sale 200,002 Amortization of capitalized software development costs from current and prior years 94,321 Expenses related to projects after technological feasibility has been established but before software is available for commercial production 151,323 Salaries and wages of programmers doing research 910,000 Expenses related…arrow_forwardKey success factors. Dominic Consulting has issued a report recommending changes for its newest manufacturing client, Casper Engines. Casper Engines currently manufactures a single product, which is sold and distributed nationally. The report contains the following suggestions for enhancing business performance: Develop a hybrid engine to stay ahead of competitors Increase training hours of assembly-line personnel to decrease the currently high volumes of scrap and waste. Reduce lead times (time from customer order of product to customer receipt of product) by 20% in order to increase customer retention. Negotiate faster response times with direct material suppliers to allow for lower material inventory levels Benchmark the company’s gross margin percentages against its major competitors. Link each of these changes to the key success factors that are important to managers.arrow_forward
- At the end of 20x1, Mejorar Company implemented a low-cost strategy to improve its competitive position. Its objective was to become the low-cost producer in its industry. A Balanced Scorecard was developed to guide the company toward this objective. To lower costs, Mejorar undertook a number of improvement activities such as JIT production, total quality management, and activity-based management. Now, after two years of operation, the president of Mejorar wants some assessment of the achievements. To help provide this assessment, the following information on one product has been gathered: Required: 1. Compute the following measures for 20x1 and 20x3: a. Actual velocity and cycle time b. Percentage of total revenue from new customers (assume one unit per customer) c. Percentage of very satisfied customers (assume each customer purchases one unit) d. Market share e. Percentage change in actual product cost (for 20x3 only) f. Percentage change in days of inventory (for 20x3 only) g. Defective units as a percentage of total units produced h. Total hours of training i. Suggestions per production worker j. Total revenue k. Number of new customers 2. For the measures listed in Requirement 1, list likely strategic objectives, classified according to the four Balance Scorecard perspectives. Assume there is one measure per objective.arrow_forwardAuflegger, Inc., manufactures a product that experiences the following activities (and times): Required: 1. Compute the MCE for this product. 2. A study lists the following root causes of the inefficiencies: poor quality components from suppliers, lack of skilled workers, and plant layout. Suggest a possible cost reduction strategy, expressed as a series of if-then statements that will reduce MCE and lower costs. Finally, prepare a strategy map that illustrates the causal paths. In preparing the map, use only three perspectives: learning and growth, process, and financial. 3. Is MCE a lag or a lead measure? If and when MCE acts as a lag measure, what lead measures would affect it?arrow_forwardKagle design engineers are in the process of developing a new green product, one that will significantly reduce impact on the environment and yet still provide the desired customer functionality. Currently, two designs are being considered. The manager of Kagle has told the engineers that the cost for the new product cannot exceed 550 per unit (target cost). In the past, the Cost Accounting Department has given estimated costs using a unit-based system. At the request of the Engineering Department, Cost Accounting is providing both unit-and activity-based accounting information (made possible by a recent pilot study producing the activity-based data). Unit-based system: Variable conversion activity rate: 100 per direct labor hour Material usage rate: 20 per part ABC system: Labor usage: 15 per direct labor hour Material usage (direct materials): 20 per part Machining: 75 per machine hour Purchasing activity: 150 per purchase order Setup activity: 3,000 per setup hour Warranty activity: 500 per returned unit (usually requires extensive rework) Customer repair cost: 25 per repair hour (average) Required: 1. Select the lower-cost design using unit-based costing. Are logistical and post-purchase activities considered in this analysis? 2. Select the lower-cost design using ABC analysis. Explain why the analysis differs from the unit-based analysis. 3. What if the post-purchase cost was an environmental contaminant and amounted to 10 per unit for Design A and 40 per unit for Design B? Assume that the environmental cost is borne by society. Now which is the better design?arrow_forward
- Jolene Askew, manager of Feagan Company, has committed her company to a strategically sound cost reduction program. Emphasizing life-cycle cost management is a major part of this effort. Jolene is convinced that production costs can be reduced by paying more attention to the relationships between design and manufacturing. Design engineers need to know what causes manufacturing costs. She instructed her controller to develop a manufacturing cost formula for a newly proposed product. Marketing had already projected sales of 25,000 units for the new product. (The life cycle was estimated to be 18 months. The company expected to have 50 percent of the market and priced its product to achieve this goal.) The projected selling price was 20 per unit. The following cost formula was developed: Y=200,000+10X1 where X1=Machinehours(Theproductisexpectedtouseonemachinehourforeveryunitproduced.) Upon seeing the cost formula, Jolene quickly calculated the projected gross profit to be 50,000. This produced a gross profit of 2 per unit, well below the targeted gross profit of 4 per unit. Jolene then sent a memo to the Engineering Department, instructing them to search for a new design that would lower the costs of production by at least 50,000 so that the target profit could be met. Within two days, the Engineering Department proposed a new design that would reduce unit-variable cost from 10 per machine hour to 8 per machine hour (Design Z). The chief engineer, upon reviewing the design, questioned the validity of the controllers cost formula. He suggested a more careful assessment of the proposed designs effect on activities other than machining. Based on this suggestion, the following revised cost formula was developed. This cost formula reflected the cost relationships of the most recent design (Design Z). Y=140,000+8X1+5,000X2+2,000X3 where X1=MachinehoursX2=NumberofbatchesX3=Numberofengineeringchangeorders Based on scheduling and inventory considerations, the product would be produced in batches of 1,000; thus, 25 batches would be needed over the products life cycle. Furthermore, based on past experience, the product would likely generate about 20 engineering change orders. This new insight into the linkage of the product with its underlying activities led to a different design (Design W). This second design also lowered the unit-level cost by 2 per unit but decreased the number of design support requirements from 20 orders to 10 orders. Attention was also given to the setup activity, and the design engineer assigned to the product created a design that reduced setup time and lowered variable setup costs from 5,000 to 3,000 per setup. Furthermore, Design W also creates excess activity capacity for the setup activity, and resource spending for setup activity capacity can be decreased by 40,000, reducing the fixed cost component in the equation by this amount. Design W was recommended and accepted. As prototypes of the design were tested, an additional benefit emerged. Based on test results, the post-purchase costs dropped from an estimated 0.70 per unit sold to 0.40 per unit sold. Using this information, the Marketing Department revised the projected market share upward from 50 percent to 60 percent (with no price decrease). Required: 1. Calculate the expected gross profit per unit for Design Z using the controllers original cost formula. According to this outcome, does Design Z reach the targeted unit profit? Repeat, using the engineers revised cost formula. Explain why Design Z failed to meet the targeted profit. What does this say about the use of unit-based costing for life-cycle cost management? 2. Calculate the expected profit per unit using Design W. Comment on the value of activity information for life-cycle cost management. 3. The benefit of the post-purchase cost reduction of Design W was discovered in testing. What direct benefit did it create for Feagan Company (in dollars)? Reducing post-purchase costs was not a specific design objective. Should it have been? Are there any other design objectives that should have been considered?arrow_forwardDecision Making Pix Paper Inc. produces photographic paper for printing digital images. One of the processes for this operation is a coating (solvent spreading) operation, where chemicals are coated onto paper stock. There has been some concern about the cost performance of this operation. As a result, you have begun an investigation. You first discover that all materials and conversion prices have been stable for the last six months. Thus, increases in prices for inputs are not an explanation for increasing costs. However, you have discovered three possible problems from some of the operating personnel whose quotes follow: Operator 1: "I've been keeping an eye on my operating room instruments. I feel as though our energy consumption is becoming less efficient." Operator 2: "Every time the coating machine goes down, we produce waste on shutdown and subsequent startup. It seems as though during the last half year, we have had more unscheduled machine shutdowns than in the past. Thus, I…arrow_forwardDecision Making Pix Paper Inc. produces photographic paper for printing digital images. One of the processes for this operation is a coating (solvent spreading) operation, where chemicals are coated onto paper stock. There has been some concern about the cost performance of this operation. As a result, you have begun an investigation. You first discover that all materials and conversion prices have been stable for the last six months. Thus, increases in prices for inputs are not an explanation for increasing costs. However, you have discovered three possible problems from some of the operating personnel whose quotes follow: Operator 1: "I've been keeping an eye on my operating room instruments. I feel as though our energy consumption is becoming less efficient."Operator 2: "Every time the coating machine goes down, we produce waste on shutdown and subsequent startup. It seems as though during the last half year, we have had more unscheduled machine shutdowns than in the past. Thus, I…arrow_forward
- Miami Training Support (MTS) produces materials for companies to use for training new hires as well as advanced training for employees who have been promoted to new positions. Most of the material has been created and produced by Miami employees. There is some unique content, however, and that material differentiates the company from competitors. MTS includes this content in all its courses. This content was created and produced by one of the founders of MTS, who is about to leave the company. As a part of the compensation agreement to be signed, MTS may continue to use the unique content, but must pay the founder (the original creator) a royalty. Many of the details have been decided, but some specific issues need to be resolved. MTS is looking to you for advice on how to structure the agreement. Specifically, MTS is considering two options for paying the royalty. The first is course based, where MTS will pay the founder $1,000 for each of the courses sold. The second is a flat,…arrow_forwardPix Paper Inc. produces photographic paper for printing digital images. One of the processes for this operation is a coating (solvent spreading) operation, where chemicals are coated onto paper stock. There has been some concern about the cost performance of this operation. As a result, you have begun an investigation. You first discover that all materials and conversion prices have been stable for the last six months. Thus, increasesin prices for inputs are not an explanation for increasing costs. However, you have discovered three possible problems from some of the operating personnel whose quotes follow:Operator 1: “I’ve been keeping an eye on my operating room instruments. I feel as though our energy consumption is becoming less efficient.”Operator 2: “Every time the coating machine goes down, we produce waste on shutdown and subsequent startup. It seems as though during the last half year, we have had more unscheduled machine shutdowns than in the past. Thus, I think our yields…arrow_forwardCain Components manufactures and distributes various plumbing products used in homes and other buildings. Over time, the production staff has noticed that products they considered easy to make were difficult to sell at margins considered reasonable, while products that seemed to take a lot of staff time were selling well despite recent price increases. A summer intern has suggested that the cost system might be providing misleading information. The controller decided that a good summer project for the intern would be to develop, in one self-contained area of the plant, an alternative cost system with which to compare the current system. The intern identified the following cost pools and, after discussion with some plant personnel, appropriate cost drivers for each pool. There were: Cost Pools Costs Activity Drivers Receiving $ 600,000 Direct material cost Manufacturing 5,500,000 Machine-hours Machine setup 900,000 Production runs Shipping 1,000,000 Units shipped…arrow_forward
- Managerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubCornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningManagerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage Learning