Given the information below, estimate the probability that the noncritical path B-C-G will take more than 15 weeks. Hint: Subtract from 1.0 the probability that B-C-G will take 15 weeks or less. Refer to the standard normal table. Activity A B E F G The probability that this path will take more than 15 weeks to complete is Expected Time (weeks) 3.5 5.0 3.5 11.5 6.5 8.5 4.5 Variance 1.00 0.69 0.15 1.78 2.40 2.55 0.69 (Enter your response rounded to four decimal places.)

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Given the information​ below, estimate the probability that the noncritical path
Upper B dash Upper C dash Upper GB-C-G
will take more than
1515
weeks. ​Hint: Subtract from 1.0 the probability that
Upper B dash Upper C dash Upper GB-C-G
will take
1515
weeks or less. Refer to the
standard normal table
LOADING...
.
 
                                                                                                      
Activity
Expected Time​ (weeks)
Variance
A
3.53.5
 
1.001.00
B
5.05.0
 
0.690.69
C
3.53.5
 
0.150.15
D
11.511.5
 
1.781.78
E
6.56.5
 
2.402.40
F
8.58.5
 
2.552.55
G
4.54.5
 
0.690.69
Part 2
The probability that this path will take more than
1515
weeks to complete is
enter your response here.
​(Enter
your response rounded to four decimal
Given the information below, estimate the probability that the noncritical path B-C-G will take more than 15 weeks. Hint: Subtract from 1.0 the probability that B-C-G will take 15 weeks or less. Refer
to the standard normal table.
Activity
A
B
E
F
G
The probability that this path will take more than 15 weeks to complete is
Expected Time (weeks)
3.5
5.0
3.5
11.5
6.5
8.5
4.5
Variance
1.00
0.69
0.15
1.78
2.40
2.55
0.69
(Enter your response rounded to four decimal places.)
Transcribed Image Text:Given the information below, estimate the probability that the noncritical path B-C-G will take more than 15 weeks. Hint: Subtract from 1.0 the probability that B-C-G will take 15 weeks or less. Refer to the standard normal table. Activity A B E F G The probability that this path will take more than 15 weeks to complete is Expected Time (weeks) 3.5 5.0 3.5 11.5 6.5 8.5 4.5 Variance 1.00 0.69 0.15 1.78 2.40 2.55 0.69 (Enter your response rounded to four decimal places.)
AI-Generated Solution
AI-generated content may present inaccurate or offensive content that does not represent bartleby’s views.
steps

Unlock instant AI solutions

Tap the button
to generate a solution

Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.