In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: 2024 2025 2026 $3,600,000 $4,050,000 $1,485,000 Cost incurred during the year Estimated costs to complete as of year-end 5,400,000 Billings during the year 3,000,000 2,350,000 Cash collections during the year 2,800,000 2,600,000 Assume that Westgate Construction's contract with Santa Clara County does not qualify for revenue recognition over time. 1,350,000 0 4,650,000 4,600,000

CONCEPTS IN FED.TAX.,2020-W/ACCESS
20th Edition
ISBN:9780357110362
Author:Murphy
Publisher:Murphy
Chapter3: Income Sources
Section: Chapter Questions
Problem 88P
icon
Related questions
Question
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2026. Information related to the contract is as follows:
2024
2025
2026
$ 3,600,000 $4,050,000
$1,485,000
Cost incurred during the year
Estimated costs to complete as of year-end
Billings during the year
Cash collections during the year
Assume that Westgate Construction's contract with Santa Clara County does not qualify for revenue recognition over time.
Required:
1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years.
2-a. In the journal below, complete the necessary journal entries for the year 2024 (credit "Cash, Materials, etc." for
construction costs incurred).
5,400,000
3,000,000 4,650,000
2,800,000
4,600,000
1,350,000 0
2,350,000
2,600,000
2-b. In the journal below, complete the necessary journal entries for the year 2025 (credit "Cash, Materials, etc." for
construction costs incurred).
2-c. In the journal below, complete the necessary journal entries for the year 2026 (credit "Cash, Materials, etc." for
construction costs incurred).
3. Complete the information required below to prepare a partial balance sheet for 2024 and 2025 showing any items
related to the contract.
4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the
following costs incurred and costs to complete information.
2024
$ 2,500,000
2025
$3,850,000
Cost incurred during the year
Estimated costs to complete as of year-end 5,700,000 3,200,000 0
5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the
following costs incurred and costs to complete information.
2024
2025
Cost incurred during the year
$ 2,500,000 $3,850,000
Estimated costs to complete as of year-end 5,700,000 4,200,000 0
2026
$3,300,000
2026
$4,050,000
Transcribed Image Text:In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: 2024 2025 2026 $ 3,600,000 $4,050,000 $1,485,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Assume that Westgate Construction's contract with Santa Clara County does not qualify for revenue recognition over time. Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. 2-a. In the journal below, complete the necessary journal entries for the year 2024 (credit "Cash, Materials, etc." for construction costs incurred). 5,400,000 3,000,000 4,650,000 2,800,000 4,600,000 1,350,000 0 2,350,000 2,600,000 2-b. In the journal below, complete the necessary journal entries for the year 2025 (credit "Cash, Materials, etc." for construction costs incurred). 2-c. In the journal below, complete the necessary journal entries for the year 2026 (credit "Cash, Materials, etc." for construction costs incurred). 3. Complete the information required below to prepare a partial balance sheet for 2024 and 2025 showing any items related to the contract. 4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs incurred and costs to complete information. 2024 $ 2,500,000 2025 $3,850,000 Cost incurred during the year Estimated costs to complete as of year-end 5,700,000 3,200,000 0 5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs incurred and costs to complete information. 2024 2025 Cost incurred during the year $ 2,500,000 $3,850,000 Estimated costs to complete as of year-end 5,700,000 4,200,000 0 2026 $3,300,000 2026 $4,050,000
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 7 steps with 10 images

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
CONCEPTS IN FED.TAX., 2020-W/ACCESS
CONCEPTS IN FED.TAX., 2020-W/ACCESS
Accounting
ISBN:
9780357110362
Author:
Murphy
Publisher:
CENGAGE L
Intermediate Accounting: Reporting And Analysis
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning