scenarios of a project activities (tables given below) and their required times to be completed in addition to their predecessors for developing a 'Hehsite': Activity Description Duration (days) Preceding Activities Determine user needs Review s/w and languages Purchase software 5 D. Design format and style Write programs Review outcome product with user Make revisions H. Select server site E Install on server D. F Test G, H, I 1. Draw the path. 2. Calculate the carly finishing time (forwards calculations) 3. Highlight the total time to complete the project (days or weeks) 4. Calculate the late finishing time (backwards calculations) 5. Calculate the slack time of the non-critical path activities 6. Identify the critical path (highlight critical path activities) 7. what would happen if revised to take seven weeks instead of five weeks

Information Technology Project Management
9th Edition
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Kathy Schwalbe
Chapter6: Project Schedule Management
Section: Chapter Questions
Problem 7E
icon
Related questions
Question
scenarios of a project activities (tables given below) and their required times to be completed in
addition to their predecessors for developing a 'Hehsite':
Activity
Description
Duration (days)
Preceding Activities
Determine user needs
Review s/w and languages
Purchase software
5
D.
Design format and style
Write programs
Review outcome product with user
Make revisions
H.
Select server site
E
Install on server
D. F
Test
G, H, I
1. Draw the path.
2. Calculate the carly finishing time (forwards calculations)
3. Highlight the total time to complete the project (days or weeks)
4. Calculate the late finishing time (backwards calculations)
5. Calculate the slack time of the non-critical path activities
6. Identify the critical path (highlight critical path activities)
7. what would happen if revised to take seven weeks instead of five weeks
Transcribed Image Text:scenarios of a project activities (tables given below) and their required times to be completed in addition to their predecessors for developing a 'Hehsite': Activity Description Duration (days) Preceding Activities Determine user needs Review s/w and languages Purchase software 5 D. Design format and style Write programs Review outcome product with user Make revisions H. Select server site E Install on server D. F Test G, H, I 1. Draw the path. 2. Calculate the carly finishing time (forwards calculations) 3. Highlight the total time to complete the project (days or weeks) 4. Calculate the late finishing time (backwards calculations) 5. Calculate the slack time of the non-critical path activities 6. Identify the critical path (highlight critical path activities) 7. what would happen if revised to take seven weeks instead of five weeks
Expert Solution
steps

Step by step

Solved in 3 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Information Technology Project Management
Information Technology Project Management
Computer Science
ISBN:
9781337101356
Author:
Kathy Schwalbe
Publisher:
Cengage Learning
Principles of Information Systems (MindTap Course…
Principles of Information Systems (MindTap Course…
Computer Science
ISBN:
9781285867168
Author:
Ralph Stair, George Reynolds
Publisher:
Cengage Learning