Which of the following statements regarding PERT times is true? Pessimistic time estimate is an estimate of the minimum time an activity will require Optimistic time estimate is an estimate of the minimum time an activity will require Most likely time estimate is an estimate of the maximum time an activity will require Optimistic time estimate is an estimate of the maximum time an activity will require
Which of the following statements regarding PERT times is true? Pessimistic time estimate is an estimate of the minimum time an activity will require Optimistic time estimate is an estimate of the minimum time an activity will require Most likely time estimate is an estimate of the maximum time an activity will require Optimistic time estimate is an estimate of the maximum time an activity will require
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter5: Network Models
Section: Chapter Questions
Problem 1C
Related questions
Question
![Question 12
Which of the following statements regarding PERT times is true?
Pessimistic time estimate is an estimate of the minimum time an activity will require
Optimistic time estimate is an estimate of the minimum time an activity will require
Most likely time estimate is an estimate of the maximum time an activity will require
Optimistic time estimate is an estimate of the maximum time an activity will require](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Fd5e12461-18b3-4490-bd62-c7f52c0b7def%2Fd1f799bf-c7c8-455e-8392-b28d049e3234%2F3mezkx5_processed.jpeg&w=3840&q=75)
Transcribed Image Text:Question 12
Which of the following statements regarding PERT times is true?
Pessimistic time estimate is an estimate of the minimum time an activity will require
Optimistic time estimate is an estimate of the minimum time an activity will require
Most likely time estimate is an estimate of the maximum time an activity will require
Optimistic time estimate is an estimate of the maximum time an activity will require
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, management and related others by exploring similar questions and additional content below.Recommended textbooks for you
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,