Chapter 20.6, Problem 2P

Explanation of Solution

Given:

  • The total cost of employing a teller at a bank is $100 per day.
  • A teller can serve an average of 60 customers per day.
  • An average of 50 customers per day arrives at the bank.
  • Both service times and inter arrival times are exponential.
  • The delay cost per customer day is $100.

To determine

The number of tellers that the bank should hire is to be determined.

Calculating the number of tellers, the bank should hire:

The queuing system is a M|M|s|GD|| system with exponential inter arrival times, exponential service times, s servers, general queue discipline, infinite capacity and infinite population size from which the customers are drawn.

Here,

Arrival rate, λ=50 customers/day

Service rate, μ=60 customers/day

Also, if there are s servers, then,

ρ = λ = 5060s = 56s

In queuing optimization problem, the component of cost due to customers waiting in line is referred to as the delay cost. Thus, the bank wants to minimize,

TotalExpectedcostDay = ExpectedservicecostDay + ExpecteddelaycostDay...(1)

Since, the total cost of employing a tell at a bank is $100 per day, then,

ExpectedservicecostDay = 100s

Case 1:

For number of servers,  s = 1.

ExpectedservicecostDay = 100 × 1 = $100.00...(2)

The Hourly delay cost is defined as follows:

ExpecteddelaycostDay=ExpecteddelaycostCustomerExpectedcustomersDay

Now, the delay cost per customer day is $100. Thus,

ExpecteddelaycostCustomer=$100Customer-dayaveragedayscustomerspendsinthesystem

                                     = 100W

Also,

ExpectedcustomersDay = λ = 50

Hence,

ExpecteddelaycostDay=$100percustomer - day50customersperdayW...(3)

      =100×50×W

Now, the average hours the customer spends in the system W for a M|M|1 queuing system is as follows:

W=1μ-λ=160-50=110days

Substituting W = 0.1 days in equation 3 to compute the expected delay cost per hour as follows:

  ExpecteddelaycostDay=$100percustomer-day50customersperdayW

                   =$100percustomer-day50customersperday(0.1day)=$500       ....(4)

Now, substitute the value obtained from equation 2 and equation 4 in equation 1,

TotalExpectedcostDay = ExpectedservicecostDay + ExpecteddelaycostDay

                            =$100.00+$500.00=$600.00

Hence, the total cost per day for one server is $600.

Case 2:

For number of servers, s = 2, the queuing system is M|M|2 queuing system is as follows:

ρ=50/120=0.41

ExpectedservicecostDay=100s=100×2=$200

Blurred answer
Students have asked these similar questions
In a service center you must first go to server 1, then to server 2, and finally to server 3. Suppose that the times for the activities in the servers are exponentially distributed with means 10, 5, and 2 minutes, respectively. What is the expected amount of time (in minutes) a customer will spend in the service center if upon arrival there is one customer with server 2 and no one at servers 1 and 3?
How do I answer this, please?  Acme Parts runs a small factory and employs workers who are paid one of three hourly rates depending on their shift: first shift, $17 per hour; second shift, $18.50 per hour; third shift, $22 per hour. Each factory worker might work any number of hours per week; any hours greater than 40 are paid at one and one-half times the usual rate. In addition, second- and third-shift workers can elect to participate in the retirement plan for which 3% of the worker’s gross pay is deducted from the paychecks. Write a program that prompts the user for hours worked, shift, and, if the shift is 2 or 3, whether the worker elects the retirement (1 for yes, 2 for no). Display: Hours worked Shift Hourly pay rate Regular pay Overtime pay Total of regular and overtime pay Retirement deduction, if any Net pay.
In a cohort of thirty graduating students, there are three different prizes to be awarded. If no student can receive more than one prize, in how many different ways could the prizes be awarded?

Chapter 20 Solutions

Operations Research : Applications and Algorithms

Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Operations Research : Applications and Algorithms
Computer Science
ISBN:9780534380588
Author:Wayne L. Winston
Publisher:Brooks Cole