Explanation of Solution
Selecting the project using the preemptive goal
Consider the following variables
For every project values related to each attribute are tabulated.
The table is given below,
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | |
ROI | 2070 | 456 | 670 | 350 | 495 | 380 | 1500 | 480 |
Cost | 900 | 240 | 335 | 700 | 410 | 190 | 500 | 160 |
Productivity improvement | 3 | 2 | 2 | 0 | 1 | 0 | 3 | 2 |
Manpower needed | 18 | 18 | 27 | 36 | 42 | 6 | 48 | 24 |
Degree of risk | 3 | 2 | 4 | 1 | 1 | 0 | 2 | 3 |
The company has the following goals.
Goal 1: Archive a return on investment of at least
Goal 2: Limit cost to
Goal 3: Archive a productivity improvement of at least 6. Thus the constraint formed is,
Goal 4: Limit manpower use to 108. Thus the constraint formed is,
Goal 5: Limit technological risk to a total of 4. Thus the constraint formed is
Hence the linear programming can be formulated as given below,
Minimize
Subject to the constraints,
Here, it is observed that for these set of constraints, there is no region which is feasible. That is all the constraints cannot be met. Hence e assign a cost value incurred if any of the goal is not meet. So introduce deviational variables as follows
Want to see the full answer?
Check out a sample textbook solutionChapter 4 Solutions
Introduction to mathematical programming
- Consider that you are developing a project where people would choose to test themselves to go without using a computer for a fixed period of time. Describe how you would set up the project and why. Would you be willing to do go "computerless"?How long do you think you could commit to?What would be particularly challenging for you to avoid?What modifications would you have to make for school?What modifications would you have to make for socializing?How would this affect others?What things could you get done?arrow_forward4 - Earned Value (EV) for a new optic radar design project is calculated at $100,000 and the Actual Cost (AC) is $80,000. The Budget at Completion (BAC) is estimated at $200,000. What is the current CPI on this project?arrow_forwardIdentify a suitable iterative methodology for the scenario given below and justify your choice. Critically evaluate the different stages of the iterative methodology chosen by mapping on to the given scenario. Identify, explain and draw the main use cases of the scenario. Assume that you are working as a project manager in a reputed organization and you have been assigned with a new project to develop a suitable system for the following scenario. A leading job recruitment and training institution in Oman would like to develop a system to manage all their functional requirements like upload the current job requirements as well the courses they have offered. The website can be used by the job seekers as well as for trainees to take up a training on any course they are offering. The system should have the features for the clients to Sign in, register, Upload CV, apply for an existing job. The website should also show all the information about a course such as course name, duration,…arrow_forward
- North Hills College is a tiny private school in Candyland. In the future, the college may replace its digital exam system. A related eight is a number assigned to a cause for a system project by the college director.arrow_forwardConsider the development of the project from two different perspectives: one without architecture, and one with it. What kind of impact it will have on the overall output.arrow_forwardYou have been appointed as a software project manager and have drained up a strategy for the main project activities, as follows. You are required to prepare the followings. 1: Program Evaluation Review Technique by using Activity on Arrow Method 2 Critical Path Method (Forward and Backward Pass) Note: There should be no redundant dummy/dummies. Activities Preceding Activities Duration (Days) A 2 B 3 ... C 1 D А. В. С 4 E D 2 F D 3 G D 4 H E. R 2 E. R 2 Н. I I 1 K E. F. G 3 G.O 2 M G.O 1 L. M N. K. O. J 3 P А. В. С А. В. С 4 R 3arrow_forward
- I need overview and need for the Project (the Project about automatic greenhouse farming system using Arduino)arrow_forwardA Hospital Management System Development Project has a budgeted cost of Rs. 22,700,000/-. The project is to be completed in 11 months. After 4 months, you have completed 24 percent of the project at a total expense of Rs. 2,925,000/-. You, as a Project Manager, needs to submit the monthly performance report to the Steering Committee. Based on EVM methodology, please identify the current progress of the Project. Find Budget at Completion (BAC), Actual Cost(AC), Planned Value (PV) and Earned Value (EV). Calculate the Project Health by finding values of Schedule Variance (SV), Schedule Performance Index (SPI), Cost Variance (CV) and Cost Performance Index (CPI). What these value shows? If the project continues at the current pace, what will be the true cost of the Project or Estimate at completion of the project. What actions, you would suggest or take as a Project Manager, to keep the budget and time under control.arrow_forwardThe ABC school recently had gone through a partial renovation. The school has 4 floors. According to the new layout, the ground floor has a reception room with 6 desks and a lecture hall. The first floor has a computer cluster with 40 PCs, a computer laboratory with 30 workstations with computer facility, a lecture hall and five staff offices. The second floor has two research laboratories for research and post-doctoral researchers. This floor had 8 staff offices and a conference room. All workstations need two data points to get connected to the internet. Each floor also requires wireless connectivity to enable the staff and students to get connected to the internet. The ABC school requires new LAN architecture for these floors. Imagine you are the network manager of theschool and required to write a report with the flowing section. i) To discuss interoperability issues for seamless connectivity to each floor, draw OSI layered architecture, discuss the OSI model, its history, and the…arrow_forward
- 11. A model-based technique for estimation wherein standard parameters based on prior projects are applied to the new project is known as a. COCOMO b. decomposition c. resource leveling d. function pointsarrow_forwardYou have been made project coordinator for an upcoming tourism workshop to be held in the island of Anguilla. Local, regional and international participants will be in attendance. You have invited 25 participants and 12 presenters as part of your planning. In addition, there are several other tasks to be performed: i. Letters of invitation are to be sent with relevant information. ii. Overall estimates for workshop funding need to be calculated. iii. During the workshop, all attendees and equipment requests will be documented for reporting purposes and also to be used for future analysis when compared with other possible workshops. iv. Final reports will be written to document those persons who attended the workshop as well as to compare the pre- and post-funding estimates. v. Extra expenses incurred at the workshop are also to be noted. vi. A brief presentation highlighting various aspects of Anguilla’s culture and island is to be made to all participants at the beginning of the…arrow_forwardI want a full research project about remote working and the problems in remote working and how we could fix these problems in the research please include:A)introductionB)objectives C)methodology D)discussion E)conclusionarrow_forward
- Operations Research : Applications and AlgorithmsComputer ScienceISBN:9780534380588Author:Wayne L. WinstonPublisher:Brooks ColeFundamentals of Information SystemsComputer ScienceISBN:9781337097536Author:Ralph Stair, George ReynoldsPublisher:Cengage LearningPrinciples of Information Systems (MindTap Course...Computer ScienceISBN:9781305971776Author:Ralph Stair, George ReynoldsPublisher:Cengage Learning