An electronic chess game has a useful life that is exponential with a mean of 30 month. Determine each of the following:

a. The probability that any given unit will operate for at least (1) 39 months. (2) 48 men the (3) 60 months.

b. The probability that any given unit will fail sooner than (1) 33 months. (2) 15 months. (3) 6 months.

c. The length of service tune after which the percentage of tilled units will approximately equal (1) 50 percent, (2) 85 percent, (3) 95 percent, (4) 99 percent.

a)

Expert Solution
Check Mark
Summary Introduction

To determine: The probability the unit will operate at least for the following times.

Introduction:

Mean time between failures (MTBF):

The mean time between failures is a term which denotes the time that is elapsed between the first failure of a product and the second failure of a product. It is calculated during the normal system operation.

Answer to Problem 12P

The probability the unit will operate at least for the following times are:

1) 39 months = 0.2725

2) 48 months = 0.2019

3) 60 months = 0.1353

Explanation of Solution

Given information:

MTBF = 30 months

Formula to calculate the probability of no failure before a time period:

Probability=e-TMTBF

Calculation of probability:

1) 39 months:

TMTBF=3930=1.3

Probability=e-TMTBF=e-1.3=0.2725

Hence, the probability the unit will operate at least for the 39 months is 0.2725.

2) 48 months:

TMTBF=4830=1.6

Probability=e-TMTBF=e-1.6=0.2019

Hence, the probability the unit will operate at least for the 48 months is 0.2019.

3) 60 months:

TMTBF=6030=2

Probability=e-TMTBF=e-2=0.1353

Hence, the probability the unit will operate at least for the 60 months is 0.1353.

b)

Expert Solution
Check Mark
Summary Introduction

To determine: The probability the unit will fail before the following times.

Introduction:

Mean time between failures (MTBF):

The mean time between failures is a term which denotes the time that is elapsed between the first failure of a product and the second failure of a product. It is calculated during the normal system operation.

Answer to Problem 12P

The probability the unit will fail before the following times are:

1) 33 months = 0.6671

2) 15 months = 0.3935

3) 6 months = 0.1813

Explanation of Solution

Given information:

MTBF = 30 months

Formula to calculate the probability of failure before a time period:

Probability=1-e-TMTBF

Calculation of probability:

1) 33 months:

TMTBF=3330=1.1

Probability=1-e-TMTBF=1-e-1.1=1-0.3329=0.6671

Hence, the probability the unit will fail before 33 months is 0.6671.

2) 15 months:

TMTBF=1530=0.5

Probability=1-e-TMTBF=1-e-0.5=1-0.6065=0.3935

Hence, the probability the unit will fail before 15 months is 0.3935.

3) 6 months:

TMTBF=630=0.2

Probability=1-e-TMTBF=1-e-0.2=1-0.8187=0.1813

Hence, the probability the unit will fail before 6 months is 0.1813.

c)

Expert Solution
Check Mark
Summary Introduction

To determine: The length of service time for the percentage of failed units.

Introduction:

Mean time between failures (MTBF):

The mean time between failures is a term which denotes the time that is elapsed between the first failure of a product and the second failure of a product. It is calculated during the normal system operation.

Answer to Problem 12P

The length of service time for the percentage of failed units is:

1) 50 percent = 21 months.

2) 85 percent = 57 months.

3) 95 percent = 90 months.

4) 99 percent = 138 months.

Explanation of Solution

Given information:

MTBF = 30 months

Formula to calculate the probability of no failure before a time period:

Probability=e-TMTBF

Calculation of probability:

Operations Management, Chapter 4.S, Problem 12P

The different probabilities are obtained from the above table.

1) 50 percent:

Probability of no failure=1-0.50=0.50

Probability=e-TMTBF0.50=e-TMTBF

From the table for the value of 0.50 is equivalent to:

TMTBF=0.70

Therefore,

T30=0.70T=0.70×0.30=21 months

Hence, the length of service time for the percentage of failed units is 21 months.

2) 85 percent:

Probability of no failure=1-0.85=0.15

Probability=e-TMTBF0.15=e-TMTBF

From the table for the value of 0.15 is equivalent to:

TMTBF=1.90

Therefore,

T30=1.90T=1.90×0.30=57 months

Hence, the length of service time for the percentage of failed units is 57 months.

3) 95 percent:

Probability of no failure=1-0.95=0.05

Probability=e-TMTBF0.05=e-TMTBF

From the table for the value of 0.05 is equivalent to:

TMTBF=3.00

Therefore,

T30=3.00T=3.00×0.30=90 months

Hence, the length of service time for the percentage of failed units is 90 months.

4) 99 percent:

Probability of no failure=1-0.99=0.01

Probability=e-TMTBF0.01=e-TMTBF

From the table for the value of 0.01 is equivalent to:

TMTBF=4.60

Therefore,

T30=4.60T=4.60×0.30=138 months

Hence, the length of service time for the percentage of failed units is 138 months.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
A local cab company maintains a fleet of 10 cabs. Each time a cab breaks down, it isrepaired the same day. Assume that breakdowns of individual cabs occur completely atrandom at a rate of two per year.d. What is the probability that there are more than five breakdowns between Thanksgiving Day (November 28) and New Year’s Day (January 1)?e. For what reason might your answer in part (d) be too low?
A weather satellite has an expected life of 10 years from the time it is placed into earth orbit. Determine its probability of no wear-out before each of the following lengths of service. Assume theexponential distribution is appropriate.a. 5 years b. 12 years c. 20 years d. 30 years
44. This risk relates to the inability to maintain critical systems and processes. Group of answer choices System capacity risk Infrastructure risk Technological and information technology risks None of the choices Data and system availability risk

Chapter 4 Solutions

Operations Management

Ch. 4.S - Consider the following system: Determine the...Ch. 4.S - A product is composed of four parts. In order for...Ch. 4.S - A system consists of three identical components....Ch. 4.S - A product engineer has developed the following...Ch. 4.S - The guidance system of a ship is controlled by a...Ch. 4.S - One of the industrial robots designed by a leading...Ch. 4.S - A production line has three machines A, B, and C,...Ch. 4.S - Prob. 8PCh. 4.S - A Web server has five major components that must...Ch. 4.S - Repeat Problem 9 under the condition that one of...Ch. 4.S - Hoping to increase the chances of reaching a...Ch. 4.S - An electronic chess game has a useful life that is...Ch. 4.S - A manufacturer of programmable calculators is...Ch. 4.S - Lucky Lumen light bulbs have an expected life that...Ch. 4.S - Prob. 15PCh. 4.S - Prob. 16PCh. 4.S - A major television manufacturer has determined...Ch. 4.S - Prob. 18PCh. 4.S - Determine the availability for each of these...Ch. 4.S - Prob. 20PCh. 4.S - A manager must decide between two machines. The...Ch. 4.S - Prob. 22PCh. 4.S - Auto batteries have an average life of 2.7 years....Ch. 4 - Prob. 1DRQCh. 4 - Prob. 2DRQCh. 4 - Prob. 3DRQCh. 4 - Prob. 4DRQCh. 4 - Prob. 5DRQCh. 4 - Prob. 6DRQCh. 4 - Prob. 7DRQCh. 4 - Prob. 8DRQCh. 4 - a. What is meant by the term life cycle? b. Why...Ch. 4 - Prob. 10DRQCh. 4 - Prob. 11DRQCh. 4 - Prob. 12DRQCh. 4 - Prob. 13DRQCh. 4 - Explain what quality function development is and...Ch. 4 - Prob. 15DRQCh. 4 - Prob. 16DRQCh. 4 - Prob. 17DRQCh. 4 - Prob. 18DRQCh. 4 - Prob. 19DRQCh. 4 - Describe some of the trade-off that are...Ch. 4 - Prob. 2TSCh. 4 - Prob. 3TSCh. 4 - Prob. 1CTECh. 4 - Prob. 2CTECh. 4 - Prob. 3CTECh. 4 - Prob. 4CTECh. 4 - Prob. 5CTECh. 4 - Give two examples of unethical conduct involving...Ch. 4 - Prob. 1PCh. 4 - Prob. 2PCh. 4 - Prepare a service blueprint for each of these...Ch. 4 - Prepare a service blueprint for each of these post...Ch. 4 - Prob. 5PCh. 4 - Prob. 6PCh. 4 - Prob. 7PCh. 4 - Prepare a table similar to that shown in Problem...
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Process selection and facility layout; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=wjxS79880MM;License: Standard YouTube License, CC-BY