Textbook Question
Chapter 7, Problem 14P
The ACWP at the end of the second week for the project in Problem 12 is $37,900. Determine the CPI for the project.
A project consists of three tasks. Task A is scheduled to begin at the start of Week 1 and finish at the end of Week 3. Task B is scheduled to begin at the start of Week 1 and finish at the end of Week 2. Task C is scheduled to begin at the start of Week 2 and end at the end of Week 3. The budgeted cost for Task A is $22,000, for Task B is $17,000, and for Task C is $15,000. At the end of the second week, Task A is 65% complete, Task B is 95% complete, and Task C is 60% complete. What is the SPI for the project at the end of the second week?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A project consists of three tasks. The budgeted cost for the three tasks are as follows:
task A is $4k, task B is $1k, and task C is $350. At the end of the first week the
following are the percentages completed: task A 50%, task B 100%, and Task C is 15%.
At the end of the first week, the actual costs of work performed was attained from
and indicates
accounting reports and amounted to $2,250. The calculated CPI is
that the project is
budget.
O 0.73, under budget
O 1.35, under budget
O 1.35, over budget
0.73, over budget
Consider the construction of 9-week foundation activity with the operation cost broken down into the following elements:
- Labor 1600 $ paid 400 $ weekly.
- Equipments 3500 $ paid 500 $ weekly after 5 weeks
- Materials 1200 $ paid 200 $ weekly after 5 weeks
- Subcontractors 1500 $ paid 300 $ weekly after 3 weeks
Determine the expenses (cash out) of this activity.
Assume any missing data
. The following seven activities constitute an overall bar chart portrayal of a six-month project.
Month 1
0.5
Month 2
Month 3
Activity
Develop Project
Charter
Cost
Month 4
Month 5
Month 6
$1,500
Develop Work
Plan
$8,000
0.5
0.5
Develop
Specifications
Design
Framework
$5,000
0.5
$15,000
Build the
$11,500
0.5
Framework
Test the
Framework
$2,000
0.5
Implement
Framework
$20,000
Note: 0.5 means half month
Three months after the start of the project, activities develop project charter, develop work
plan, develop specifications, 70% of design and 20% of building were completed for a cost
of $28,500. Evaluate the status of the project. For this project, using earned value concepts
determine the percent schedule variance, the percent cost varjance, cost performance index,
schedule performance index, the percentage completion, and estimate at completion. State if
the project is over or under budget and if it is ahead or behind schedule. (show detail
calculation)
Chapter 7 Solutions
Construction Accounting And Financial Management (4th Edition)
Ch. 7 - What are the key steps in the monitoring and...Ch. 7 - What does it indicate when a superintendent has to...Ch. 7 - What is the best way to control labor costs? What...Ch. 7 - Why are equipment costs for company-owned...Ch. 7 - What is an internai change order and how is it...Ch. 7 - Why is it important to have a realistic budget for...Ch. 7 - What are some of the problems with using the CPI?Ch. 7 - Prob. 8DQCh. 7 - During the design phase, what are the steps for...Ch. 7 - Determine the estimated cost of the work performed...
Ch. 7 - Determine the estimated cost of the work performed...Ch. 7 - A project consists of three tasks. Task A is...Ch. 7 - A project consists of six tasks. Task A is...Ch. 7 - The ACWP at the end of the second week for the...Ch. 7 - A project consists of six tasks. Task A is...Ch. 7 - Determine the total estimated cost at completion...Ch. 7 - A project consists of six tasks. Task A is...Ch. 7 - Prob. 18P
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- An engineering company was awarded a project with an original budget of 250,000 hours, valued at $20,000,000. The Client has asked the project to prepare an in-depth analysis of the project performance and make a formal presentation. Use the following data to prepare the reports and presentation as requested by the Client. Planned hours 110,786 Actual hours spent to date 123,241 % complete 34% How many hours have the project earned?arrow_forwardA company currently in the 3rd month of a 2 year project. The financial committee would like to have a cost status report. At this stage of the project there is an estimated planned value of 37500. The rate of performance is determined at 95% and the current costs have accumulated to 400000. Determine the Budget at completion)arrow_forwardThe ABC company has the following estimated costs for the next year: Direct materials: $15,000 Indirect materials: $5,000 Direct labor: $55,000 Salary of production supervisor: $35,000 Rent on factory equipment: $16,000 Sales commission: $75,000 Advertising expenses: $11,000 It is estimated that 53,000 machine hours and 8,000 direct labor hours will be worked during the next year. What will be the predetermined overhead rate if company applies manufacturing overhead cost to jobs on the basis of direct labor hours. Select one: a. $14 b. $17 C. $7 d. $15 23°C uaoarrow_forward
- consider the following summary interim cost reports of a project, say in week 10. Assume that A, B, C and D are the only work packages in the project. Activity Total Budgeted cost for the activity Budgeted cost of work scheduled (PV) % Complete Actual Cost EV CV SV A $1,000 $1,000 100 $1,100 B $1,000 $700 50 $900 C $1000 $0 0 $0 D $1,000 $500 60 $400 (Hint: One of the columns gives you PV directly. There is no need to separately calculate it.) a) Calculate the EV, CV and SV for each activity . What is your assessment of the progress of each activity? Calculate the EV, CV, SV, CPI and SPI for the project, and the critical ratio (CR). What is your assessment of the entire project so far based on these calculations? b) There are several formulae available for calculation of the Estimated (remaining cost) to completion (ETC). Once you have ETC, you can calculate…arrow_forwardThe following were the data obtained by the manager for the first 3 quarters for 2020: Maintenance Machine Quarter Costs Hours 1st quarter 1,520,000 50,000 2nd quarter 1,718,300 62,000 3rd quarter 1,526,000 46,000 How much is the expected maintenance costs for November 2020, if the expected machine hours is 33,000?arrow_forwardA Hospital Management System Development Project has a budgeted cost of Rs. 11,900,000/-. The project is to be completed in 11 months. After 4 months, you have completed 24 percent of the project at a total expense of Rs. 1,475,000/-. You, as a Project Manager, needs to submit the monthly performance report to the Steering Committee. Based on EVM methodology, please identify the current progress of the Project. Find Budget at Completion (BAC), Actual Cost(AC), Planned Value (PV) and Earned Value (EV). Calculate the Project Health by finding values of Schedule Variance (SV), Schedule Performance Index (SPI), Cost Variance (CV) and Cost Performance Index (CPI). What these value shows? If the project continues at the current pace, what will be the true cost of the Project or Estimate at completion of the project. What actions, You would suggest or take as a Project Manager, to keep the budget and time under control.arrow_forward
- The overhead costs for a company are presently $Xper month. The management team of the company, in cooperation with the employees, is ready to implement a comprehensive improvement program to reduce these costs. If you (a) consider an observation of actual overhead costs for one month analogous to an output unit, (b) estimate the overhead costs for the first month of program implementation to be 1.15Xdue to extra front-end effort, and (c) consider a 90% improvement curve applicable to the situation, what is your estimate of the percentage reduction in present overhead costs per month after 30 months of program implementation?arrow_forwardSIS Technologies currently allocates insurance costs on the basis of direct labor hours. If the direct labor hours for departments A, B, and C are expected to be 3000, 9000, and 5000, respectively, this year, determine the allocation to each department based on an indirect cost budget of $34,000.arrow_forwardA local engineering firm is bidding on a design project for a new client. The total budgeted direct-labor costs for the firm are $600,000. The total budgeted indirect costs are $800,000. It is estimated that there are 10,000 billable hours in total. a. What is the budgeted direct-labor cost rate? b. What is the budgeted indirect-cost rate assuming direct-labor cost is the allocation base? c. What should be the engineering firm bid on the project if the direct labor hours are estimated at 300 hours?arrow_forward
- Company 10, a local road building contractor, had budgeted indirect costs for 2023 of $600,000. Budgeted labour hours for the year were 12,500 costing $260,000 and budgeted machine hours were 14,000. The company marks-up the total cost of each job by 40% to determine selling price. The company has just completed a road repair for the local council. The direct costs were as follows: Materials: $32,100 Labour: 305 hours Machining: 75 hours What is the total selling price of this job assuming the company allocates overheads on: A labour hour basis? A machine hour basis? (1) (ii) A B C D (1) Labour hour basis $53,084 $74,318 $65,436 $20,496 (ii)Machine hour basis $41,659 $58,323 $49,441 $4,521arrow_forwardQuick Construction Company builds bridges and uses the percentage of completion method. Data on its latest bridge project shows the following: Total amount of contract awarded for building the bridge = $17,400 Estimated costs to build the bridge are $10,000 The following cost pattern was incurred in the 3 months to build the bridge (20% in month 1, 30% in month 2 and 50% in month 3). Payment is due 40 days after receiving the certification that a certain percentage has been completed by month end. Required 1: Assuming no other transaction happened, what is the balance of Accounts Receivables at the end of the first month? $ Required 2: Assuming no other transaction happened, what is the balance of Accounts Receivables at the end of the second month? $ Required 3: Assuming no other transaction happened, what is the balance of Accounts Receivables at the end of the third month? $arrow_forwardJimbo has three production departments and a support department. The budgeted production overhead cost for the year ended 31st December 2020 is as follows: $ Indirect wages Department Assembly Department Painting Department Packaging Support Department 23,000 30,000 26,000 18,800 To be allocated Other cost Consumable materials 20,000 Insurance: Plant 30,000 Depreciation: Plant 22,000 Power 15,000 Rent 21,000 Light and heat 14,000 The following is the data of an appropriate basis of apportionment: Department Department Department Painting 15,000 Support Department 12,500 Assembly Packaging Floor space (m2) Book value of plant($) 22,500 20,000 140,000 180,000 70,000 10,000 Electricity Kwhs 80 100 15 5 Machine hours 110,000 150,000 140,000 Number of store 180 120 100 requisitions (materials) Direct labour hrs 80,000 120,000 100,000 The support department's overhead should be apportioned based on direct labour hours. Required: a) Prepare the overhead analysis statement showing clearly the…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education
Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,
Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON
Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education
Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education
Responsibility Accounting| Responsibility Centers and Segments| US CMA Part 1| US CMA course; Master Budget and Responsibility Accounting-Intro to Managerial Accounting- Su. 2013-Prof. Gershberg; Author: Mera Skill; Rutgers Accounting Web;https://www.youtube.com/watch?v=SYQ4u1BP24g;License: Standard YouTube License, CC-BY