The following table contains information related to the car problems of 2 SUV being maintained in Toyota. Activity Immediate Time (days) Total Cost Maximum Crash cost per day Predecessor Normal Crash Normal Crash Reduction in Duration time A 4 P1,500 P2000 В A 1000 1400 C 8 4 1600 2200 C 4 2 900 1150 E В, D 3 1 800 1300 What is the expected project duration?
Q: The following table provides the information necessary to construct a project network diagram and…
A: Project crashing is a process which reduces the total duration using additional costs. Here, we can…
Q: scenarios of a project activities (tables given below) and their required times to be completed in…
A: In this question is about the critical path where we have to make a network diagram and have to show…
Q: Three activities are candidates for crashing on a project network for a large computer installation…
A: Crash cost per day = (Crash cost - Normal cost) / (Normal time - crash cost)
Q: The diagram below was developed for the project launch of Kitty Condo, a new product in the luxury…
A: Find the Given details below: Activity Normal duration (NT) (Days) Normal cost (NC) ($) Crash…
Q: A E Start Finish B D F G Activity | A А В C D E F G Time 3 5 5 6 he crashing data for this project…
A: Critical path activity-
Q: Paul Silver, owner of Sculptures International, just initiated a new art project. The following data…
A: a. The network diagram for the project is:
Q: snip
A: Note: Since you have posted a question with multiple sub-parts, we will solve the first three…
Q: 2. As project manager, you need to reduce the project duration as requested by the client. To make…
A: Given data is
Q: 9.A Sample of EARNED VALUE ANALYSIS The following project is at the end of its 5 week.Find the cost…
A: NOTES: 1.0 CR = (actual progress/scheduled progress) x (budgeted cost/actual cost).…
Q: please help, project management 1) Given the following information for a one-year project, answer…
A: This question is related to the topic Project Management and This topic falls under the…
Q: A local grocery store plans on holding a big sales event at the end of season. The activities that…
A: Given - Activity Duration (Weeks) Immediate Predecessor A 3 - B 1 A C 4 A D 2 B E 3 D,…
Q: You are provided with the following information for a project, with activity durations given in…
A: Given that: Activity Immediate Predecessor Optimistic Time (a) Most Likely Time (m)…
Q: d. The partners have decided that shortening the project by two days would be beneficial, as long as…
A:
Q: 5) Draw the Network and do the analysis Using the information in Table 1, assuming that the project…
A: Note: - Since we can answer only up to 3 subparts, we will answer sub part i, ii, and iii for…
Q: Define a process in project management with the help of an example?
A: Project management: Project management is defined as it is a structured process of…
Q: Solve the following project by hand and submit your notes: Activity Normal Time (weeks) Crash…
A: NOTE: AS PER GUIDELINES, WE ARE ONLY ALLOWED TO DO THREE SUB-PARTS AT A TIME. PLEASE POST THE REST…
Q: Subject: Critical Path Method as a Project Management Technique Please answer the following…
A: Given data is
Q: Q1: For the project listed below, find the following items: 1- Total project finishing time 2-…
A: A critical path indicating the longest duration path which representing minimum time required to…
Q: Given the following project: Activity Predecessor Normal Time (day) Normal Cost ($) Crash…
A: Note: - Since the exact question to be answered is not specified, we will answer the first question…
Q: For the following table and report make earned value analysis to this project and represent the…
A: The answer is as below:
Q: nd throughout a project. 2. For each project phase identified in 1(a) above, identify and describe…
A: The project life cycle contains the processes necessary for project managers to effectively manage a…
Q: General Foundry’s project crashing data are shown below. Crash this project to 13 weeks using CPM.…
A: From the given data, Determining the crash slopes : TIME (WEEKS) COST ($)…
Q: What is a cost baseline in project management? How can it be applied to monitor and control a…
A: When a project is initiated there are some basic factors that are predefined like scope, budget, and…
Q: What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance…
A: WE ARE ALLOWED TO DO THREE SUB-PARTS ONLY. THE ANSWER IS AS BELOW:
Q: Davison Construction Company is building a luxury lakefront home in the Finger Lakes region of New…
A: “Since you have posted a question with multiple sub-parts, we will solve first three sub-parts for…
Q: The diagram below was developed for the project launch of Kitty Condo, a new product in the luxury…
A: Project paths Normal duration A-D-G 29 A-E-H 31 B-F-H 27 C-I-H 25 Critical…
Q: Given the following table, construct a network diagram, either AOA or AON. Times are in days.a.…
A:
Q: Activity Predecessor Duration A. 5 A 12 20 15 B 15 F D, E 10 G F 18 F 12 G,H 8. A,
A: A network diagram visually presents the activities, along with their order and duration, that must…
Q: In the project considered here, activity crashing can take place over a wide range of reduction…
A: Given details: Let's consider the amount in hundreds to make the calculation easier.
Q: Given the project information in the following table, what is the probability of completing the…
A: THE ANSWER IS AS BELOW:
Q: Ql: For activitics shown in table below, find the new time of project after updating, if the project…
A: ANSWER IS AS BELOW:
Q: The diagram in Figure was developed for the project launch of Kitty Condo, a new product in the…
A:
Q: Reliable Garage is completing production of the J2000 kit car. The following data are available for…
A:
Q: The following activities represent a small project to be constructed Normal Duration Previous (…
A: Given data is
Q: Dave is the project manager for a construction project that is building a gazebo. When the project…
A: Since the project absolutely must be completed in 7 months for it to be worth doing, the deadline is…
Q: ABC is one of the construction company and they are experiencing a huge idle time and cost overrun…
A: The given problem is Activity ImmediatePredecessors NormalTime NormalCost CrashTime CrashCost A…
Q: The company wants to implement the new project. The following are the activities required to 3.…
A:
Q: The production line project consists of nine major activities. Activity B D E Immediate Predecessor…
A: 1. During forward pass in case of more than two preceding activities the early start will be…
Q: 3. Draw a project network from the following information. What activity(s) is a burst activity? What…
A: A network diagram is the graphical representation of project activities or tasks and their duration…
Q: The table below shows a small project of 9 activities with the following time estimates: Most…
A: Given Information:
Q: [Project Management] Because a housing project is running late, the developer will need to complete…
A: Given Activity prior normal days crash days A - 9 9 B A 9 9 C B 14 12 D B 18 11 E…
Q: Ql: For activities shown in table below, find the new time of pro project manager decided to update…
A: Given that: Activities A-J What to do: First: Find the Critical path of the activities. Second:…
Q: 2. Assume the following project data given in Table 2. It is required to crash the project duration…
A: Hi, We are supposed to answer three subparts at a time. Since you have not mentioned which subpart…
Q: 3. Activities of a project are summarized in the following table. Activity Immediate Duration…
A: a) The network diagram is as follows: The critical path is: B-F-H The project completion time is 24…
Q: The table below show a set of activities of an IS project,its expected completion time (ET) and…
A: 1. Activity Immediate Predecessors Duration A - 7 B A 9 C A , B 5 D C 17 E C 12 F C 7…
Q: For each of the following network diagrams, determine both the critical path and the expected…
A: Since we only answer up to 3 sub-parts, we'll answer the first 3. Please resubmit the question and…
Q: The network dlagram and task times for a project are shown below. A2 A4 A5 A3 Task Duration (days)…
A: Using Forward Path, find Early Start of the activity = Early Finish of predecessor activity Early…
Q: The following project has a critical path of ACD with an expected duration of 10 weeks and a…
A: Activity Predecessors Mean cost Std. Dev A None 5 2 B A 4 1.5 C A 7 2.75 D B, C 2 0.5
Step by step
Solved in 3 steps with 2 images
- Stinnett Transmissions, Incorporated, has the following estimates for its new gear assembly project: Price $1,220 per unit; variable costs = $3.75 million; quantity = 90,000 units. Suppose the company believes all of its estimates are accurate only to within ±15 percent. What values should the company use for the four variables given here when it performs its best-case scenario analysis? What about the worst-case scenario? Pls don't copy answer i give up voteWhat is the minimum cost of crashing the following project at Sawaya Robotics by 4 days? NORMAL TIME (DAYS) CRASH TIME (DAYS) 5 4 ACTIVITY Design (A) Wiring (8) Chip install (C) 7 5 3 4 7 2 2 4 NORMAL COST 300 900 500 CRASH COST 1,100 1,200 350 975 575 Software (D) Testing (E) The minimum cost of crashing the following project at Sawaya Robotics by 4 days is $1,875 (enter your response as a whole number). IMMEDIATE PREDECESSOR(S) 1,300 1,650 A, B сA company that makes food-friendly silicone (for use in cooking and baking pan coatings)is considering four independent projects shown, all of which can be considered to be viable for only 10 years. The company's MARR is 15% per year. Project A B C D First Cost, $ -1500 -2300 -5600 -7600 Annual net Income, $/year 200 460 1150 1200 Salvage value, $ 5 6 8 7 Determine which products to implement Financial values are in $1000 units. The present worth of project A is $___________, So project A is ___________(Rejected / Accepted) The present worth of project B is $___________, So project B is ___________(Rejected / Accepted) The present worth of project C is $___________, So project C is ___________(Rejected / Accepted) The present worth of project D is $___________, So project D is ___________(Rejected / Accepted)
- The expected times and variances for the activities for a project for Test Marketers, Inc. are given below. (Assume time is provided in days.) ID 12345678 Description Pilot production Select channels of distrib. Develop mktg. program Test market Patent Full production Ad promotion Release Predecessor None None None 1 1 4 3 2,5,6,7 t₂ 6 7 4 4 10 16 3 2 Varlance [(b-a)/6]² 34225221 10Based on the following table. Bid Ask EURUSD 1M FWD 7.05 7.34 EURUSD 2M FWD 14.99 15.15 EURUSD 3M FWD 22.57 23.05 EURUSD 4M FWD 30.25 30.55 EURUSD 5M FWD 38.03 38.43 EURUSD 6M FWD 45.91 47.2 EUR/USD Spot 1.1411 1.1422 What is the average annualized forward premium/discount for the EUR if you use the 3M forward contract (Format for answer: X.XX% or –X.XX%)10.6 This optional problem requires knowledge of statistics. Heywood Home Healthcare is evaluating a project with the following net cash flows and probabilities: Time 0 Year 1 Year 2 Year 2 Year 3 Year 4 Prob = 0.2 ($100,000) 20,000 20,000 20,000 20,000 30,000 Prob = 0.6 ($100,000) 30,000 30,000 30,000 30,000 40,000 Prob = 0.2 ($100,000) 40,000 40,000 40,000 40,000 50,000 The year 5 values include salvage value. Heywood’s corporate cost of capital is 10 percent. What is the project’s expected NPV on the basis of the scenario analysis? What is the project’s standard deviation of NPV? Assume that Heywood’s managers judge the project to have lower-than-average risk. Furthermore, the company’s policy is to adjust the corporate cost of capital up or down by 3 percentage points to account for differential risk. Is the project financially attractive?
- MASTERY PROBLEM / Cr. Cash: $4,301.83 ar Ban Trenkamp owns and operates the Trenkamp Collection Agency. Listed below are the name, number of allowances claimed, marital status, information from time cards on hours worked each day, and the hourly rate of each employee. All hours worked in excess of 40 hours for Monday through Friday are paid at 1½ times the regular rate. All weekend hours are paid at double the regular rate. Trenkamp uses a weekly federal income tax withholding table (see Figure 8-4 on pages 288 and 289). Social Security tax is withheld at the rate of 6.2% for the first $110,100 earned. Medicare tax is withheld at 1.45% and state income tax at 3.5%. Each employee has $5 withheld for health insurance, All employees use payroll deduc- tion to the credit union for varying amounts as listed. GENERAL LEDGER Trenkamp Collection Agency Payroll Information for the Week Ended November 18, 20-- Credit Total Hourly Rate Earnings 1/1-11/11 Union Employee No. No of Allow. Regular…An R&D project in a company is working on a project to make a sample product to be displayed at an international fair in Las Vegas held in 18 months. With additional equipments, the company can make sure they make the sample in 18 months. Develop an optimal crashing time-cost solution to help the company in this project to be ready on time for the fair. C, 4 B, 3 А,5 H,7 D, 3 F, 9 G, 2 Cost per month Activity Normal Time to crash 9,000 4,000 6,000 4,000 2,000 5,000 2,000 9,000 A В C 4 E F 9. G 2 H 7 Duration Path Activity to crash (months) АВСН ADEH FGHWhat is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Normal Cost $800 $200 $600 $750 $1,200 Normal Crash Activity Time (days) Time (days) 4 3 8 6 The total cost of crashing the project by 4 days is $ ABCDE 487 355 (Enter your response as a whole number.) Total Cost with Crashing Immediate Predecessor(s) $1,500 $1,650 By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers.) Each Activity Should be Reduced BY (days) Activity A B C D E $1,100 $600 $650 A C
- 1. Decision Rules. A company is choosing a motorized mechanism for a new toy, a dancing ballerina (TippiToes) that is currently under development. Demand is uncertain. but the company is confident that demand will be: Light (25,000 units), Moderate (100,000 units) or Heavy (150,000) units. The payoff table for each mechanism (in $) is given below. Action: Choice of Mechanism Event Gears and Levers Spring Weights and Pulleys Pneumatic Light 25,000 -10,000 -125,000 -300,000 Moderate 400,000 440,000 400,000 300,000 Heavy 650,000 740,000 750,000 700,000 Questions: (1) Apply Maximax, Maximin, Minimax Regret, and EMV rules (assuming that the probability of Light demand is 0.1, Moderate demand is 0.7, and Heavy demand is 0.2) to decide what mechanism should the company choose? (2) What is the expected value of perfect information? (3) Draw a decision tree to solve this problem.an engineer proposes to spend $95,000 on a capital project to upgrade a package delivery system. The project is expected to have labor savings of $20,000 a year plus reduce scrap costs by $5,000 a year. There is expected to be no salvage value at the end of the equipment life, which is anticipated to be 7 years. MARR is 12% What is the present worth of this project?Company: ABC Civil Engineering - an engineering firmSituation: ABC company has recently made significant cuts in staff and the workload on existingemployees has increased. A major RFP is dueCharacters: Ted Waltz – Managing Director of ABC EngineeringElaine Tillman – Civil Engineer____________________________Elaine Tillman looked at her watch – it was 7:30 pm. Just then she knew she would not make it to her son’s final high school basketball game. It took her a moment to collect herself and wipe the tear that had started down her face and onto the ragged-edged 100 plus page RFP she was working on. The RFP,the largest opportunity that ABC Civil Engineering had a chance to bid on in 6 months, was far fromready for the 9:00 AM deadline the following day.Normally in this situation, Elaine would have collaborated with a proposal team putting together such a big proposal but, since the economic down turn hit, ABC has had to make significant cuts in its staff. It started with administrative…